BROOKLYN PARK PHASE II
by EKTA PARKSVILLE HOMES PVT. LTD.
Company
Project Information
RERA Certificate No.
P99000000110
Registration No.
REA99000002565
Registration Date
2017-07-04
Developer
EKTA PARKSVILLE HOMES PVT. LTD. Company
Architect
Samir
Project Bank
HDFC BANK
Proposed Possession
2019-10-31
Revised Possession
2019-10-31
Extended Possession
2023-09-30
Units Sold
0
Buildings
3
Project Area
1063.98 sq.m
Total FSI
9295.49
Approved FSI
9295.49
BROOKLYN PARK PHASE II
MahaRERA — P99000000110
MahaRERA — P99000000110
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors14
✅Sanctioned14
🅿️Closed Parking1
📅Completion2019-10-31
🏗️Proposed Floors14
✅Sanctioned14
🅿️Closed Parking1
📅Completion2019-10-31
🏗️Proposed Floors14
✅Sanctioned14
🅿️Closed Parking1
📅Completion2019-10-31
Apartment Configurations
None
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 Bhk | 33.869998931884766 | 0 | 0 | 0 | 0% |
| 1 Bhk | 34.33000183105469 | 0 | 0 | 0 | 0% |
| 1Bhk | 35.4900016784668 | 0 | 0 | 0 | 0% |
| 2 Bhk | 50.720001220703125 | 0 | 0 | 0 | 0% |
| 2Bhk | 50.720001220703125 | 0 | 0 | 0 | 0% |
| Shoptype1 | 10.579999923706055 | 0 | 0 | 0 | 0% |
| Shoptype2 | 13.300000190734863 | 0 | 0 | 0 | 0% |
| Shoptype3 | 17.3700008392334 | 0 | 0 | 0 | 0% |
| Shoptype4 | 9.789999961853027 | 0 | 0 | 0 | 0% |
| Shoptype5 | 11.1899995803833 | 0 | 0 | 0 | 0% |
| Shoptype6 | 15.449999809265137 | 0 | 0 | 0 | 0% |
| Shoptype7 | 14.069999694824219 | 0 | 0 | 0 | 0% |
Sec Iii Building No 9 Wing G
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 34.33 | 24 | 24 | 0 | 100% |
| 1 BHK | 35.49 | 12 | 12 | 0 | 100% |
| 2 BHK | 50.72 | 47 | 46 | 1 | 98% |
| SHOPTYPE1 | 10.58 | 2 | 2 | 0 | 100% |
| SHOPTYPE2 | 13.3 | 2 | 1 | 1 | 50% |
| SHOPTYPE3 | 17.37 | 4 | 4 | 0 | 100% |
| SHOPTYPE4 | 9.79 | 1 | 1 | 0 | 100% |
| SHOPTYPE5 | 11.19 | 1 | 1 | 0 | 100% |
| SHOPTYPE6 | 15.45 | 1 | 1 | 0 | 100% |
| SHOPTYPE7 | 14.07 | 1 | 1 | 0 | 100% |
Sec Iii Building No 9 Wing H
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 34.33 | 24 | 24 | 0 | 100% |
| 1 BHK | 35.49 | 12 | 12 | 0 | 100% |
| 2 BHK | 50.72 | 47 | 30 | 17 | 64% |
Sec Iii Building No 9 Wing I
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 33.87 | 47 | 47 | 0 | 100% |
Construction Progress
SEC III BUILDING NO 9 WING G
Sec Iii Building No 9 Wing G
SEC III BUILDING NO 9 WING G
Sec Iii Building No 9 Wing G
SEC III BUILDING NO 9 WING G
Sec Iii Building No 9 Wing G
SEC III BUILDING NO 9 WING G
Sec Iii Building No 9 Wing G
SEC III BUILDING NO 9 WING G
Sec Iii Building No 9 Wing G
SEC III BUILDING NO 9 WING G
Sec Iii Building No 9 Wing G
SEC III BUILDING NO 9 WING H
Sec Iii Building No 9 Wing H
SEC III BUILDING NO 9 WING H
Sec Iii Building No 9 Wing H
SEC III BUILDING NO 9 WING H
Sec Iii Building No 9 Wing H
SEC III BUILDING NO 9 WING H
Sec Iii Building No 9 Wing H
SEC III BUILDING NO 9 WING H
Sec Iii Building No 9 Wing H
SEC III BUILDING NO 9 WING H
Sec Iii Building No 9 Wing H
SEC III BUILDING NO 9 WING I
Sec Iii Building No 9 Wing I
SEC III BUILDING NO 9 WING I
Sec Iii Building No 9 Wing I
SEC III BUILDING NO 9 WING I
Sec Iii Building No 9 Wing I
SEC III BUILDING NO 9 WING I
Sec Iii Building No 9 Wing I
SEC III BUILDING NO 9 WING I
Sec Iii Building No 9 Wing I
SEC III BUILDING NO 9 WING I
Sec Iii Building No 9 Wing I
RERA Registered Amenities
⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical Meter Room, Sub-Station, Receiving Station100%
✅Energy management100%
✅Fire Protection And Fire Safety
Requirements100%
✅Landscaping & Tree Planting100%
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)100%
✅Solid Waste Management And Disposal100%
✅Storm Water Drains100%
⬜Street Lighting
✅Treatment And Disposal Of Sewage And Sullage Water100%
✅Water Conservation, Rain water Harvesting100%
✅Water Supply100%