Project Information

RERA Certificate No.
P51800032348
Registration No.
REA51800100394
Registration Date
2021-12-29
Developer
Acme Metal Industries Pvt Ltd Company
Architect
Rasik P Hingoo Associates
Project Bank
HDFC BANK
Proposed Possession
2025-06-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
2949.80 sq.m
Total FSI
6317.40
Approved FSI
399.12
MahaRERA QR
36 Allure
MahaRERA — P51800032348
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors23
Sanctioned23
🅿️Closed Parking8
📅Completion2025-06-30

Apartment Configurations

36 Allure

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK37.6320155
75%
1 BHK39.0223158
65%
2 BHK50.63110
100%
2 BHK53.1413130
100%
2 BHK54.99972
78%
2 BHK55.2817143
82%
2 BHK55.92734
43%
2 BHK56.29725
29%
2 BHK57.4116106
62%
2 BHK60.85752
71%
Office space96.71413
25%

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1Bhk37.630001068115234000
0%
1Bhk39.02000045776367000
0%
2Bhk50.630001068115234000
0%
2Bhk53.13999938964844000
0%
2Bhk54.9900016784668000
0%
2Bhk55.279998779296875000
0%
2Bhk55.91999816894531000
0%
2Bhk56.290000915527344000
0%
2Bhk57.40999984741211000
0%
2Bhk60.849998474121094000
0%
Office Space96.70999908447266000
0%

Construction Progress

36 ALLURE

Basement (if any)100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.40%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.25%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises38%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure67%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%

36 Allure

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate25%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises38%
Overall Percentage of Completion of the work done For the entire Building /Wing52%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.50%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing40%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure67%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.