RERA: A51800043517

Sheth Avalon - Phase 1

by Sheth Developers Private Limited Company
Certificate SignedP51700001729

Project Information

RERA Certificate No.
P51700001729
Registration No.
REA51700006843
Registration Date
2021-09-09
Developer
Sheth Developers Private Limited Company
Architect
Anil Jagwani
Project Bank
INDUSIND BANK
Proposed Possession
2021-12-30
Revised Possession
2021-12-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
5
Project Area
17024.53 sq.m
Total FSI
36099.04
Approved FSI
25709.93
MahaRERA QR
Sheth Avalon - Phase 1
MahaRERA — P51700001729
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors33
Sanctioned33
🅿️Closed Parking110
📅Completion2020-12-31
🏗️Proposed Floors33
Sanctioned33
🅿️Closed Parking110
📅Completion2020-12-31
🏗️Proposed Floors33
Sanctioned33
🅿️Closed Parking110
📅Completion2020-12-31
🏗️Proposed Floors31
Sanctioned31
⬇️Basements1
🅿️Closed Parking281
📅Completion2020-12-31
🏗️Proposed Floors31
Sanctioned31
⬇️Basements1
🅿️Closed Parking281
📅Completion2020-12-31

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2Bhk68.4000015258789000
0%
2Bhk68.58000183105469000
0%
2Bhk68.66000366210938000
0%
3Bhk95.63999938964844000
0%
3Bhk120.83999633789062000
0%
4Bhk150.83999633789062000
0%
4Bhk175.66000366210938000
0%
Shop87.69999694824219000
0%
Shop88.76000213623047000
0%
Shop93.2699966430664000
0%
Shop93.30999755859375000
0%

Tower D

TypeCarpet (sq.ft)TotalBookedAvailableStatus
4 BHK150.8422220
100%
4 BHK175.6628271
96%

Tower E

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3 BHK95.6422211
95%
3 BHK120.8428280
100%

Tower F

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3 BHK95.6422220
100%
3 BHK120.8428280
100%

Tower G

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK68.459590
100%
2 BHK68.5830300
100%
2 BHK68.6624240
100%
Shop87.7110
100%
Shop88.76110
100%
Shop93.27110
100%
Shop93.31110
100%

Tower H

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK68.459590
100%
2 BHK68.5830300
100%
2 BHK68.6624231
96%
SHOP87.7110
100%
Shop88.76110
100%
Shop93.27110
100%
Shop93.31110
100%

Construction Progress

TOWER D

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.99%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

TOWER E

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.98%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

TOWER F

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.98%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

TOWER G

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

TOWER H

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

RERA Registered Amenities

Aggregate area of recreational Open Space95%
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station98%
Energy management100%
Fire Protection And Fire Safety Requirements95%
GYMNASIUM SWIMMING POOL CLUB HOUSE AND OTHER RECREATION FACILITIES
Landscaping & Tree Planting98%
Open Parking90%
Sewerage (Chamber, Lines, Septic Tank , STP)100%
Solid Waste Management And Disposal95%
Storm Water Drains98%
Street Lighting100%
Treatment And Disposal Of Sewage And Sullage Water98%
Water Conservation, Rain water Harvesting100%
Water Supply95%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly