Project Information

RERA Certificate No.
P51700005696
Registration No.
REA51700008119
Registration Date
2017-08-11
Developer
Jnm Enterprises Partnership
Architect
Ten Folds
Project Bank
TJSB SAHAKARI BANK LTD
Proposed Possession
2018-08-31
Revised Possession
2018-08-31
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
535.12 sq.m
Total FSI
787.83
Approved FSI
787.83
MahaRERA QR
Sahakar Niwas
MahaRERA — P51700005696
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors9
Sanctioned9
🚗Open Parking1
🅿️Closed Parking12
📅Completion1900-01-01

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 Bhk34.83000183105469000
0%
1Rk18.149999618530273000
0%
1Rk25.440000534057617000
0%
1Rk26.350000381469727000
0%
2Rk34.369998931884766000
0%
2Rk36.81999969482422000
0%
3Rk45.790000915527344000
0%
Shop27.75000
0%

Sahakar Niwas

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK34.83642
67%
1RK18.15110
100%
1RK25.44110
100%
1RK26.35110
100%
2RK34.37514
20%
2RK36.82541
80%
3RK45.79110
100%
SHOP27.75110
100%

Construction Progress

SAHAKAR NIWAS

Basement (if any)100%

Sahakar Niwas

Excavation100%

SAHAKAR NIWAS

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Sahakar Niwas

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate85%

SAHAKAR NIWAS

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Sahakar Niwas

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%

SAHAKAR NIWAS

Plinth100%
Podiums (if any) 0%

Sahakar Niwas

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises95%

SAHAKAR NIWAS

Sanitary Fittings within the flats / premises95%
Slabs of Super Structure100%

Sahakar Niwas

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.95%

SAHAKAR NIWAS

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%

Sahakar Niwas

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting100%
Open Parking100%
Sewerage (Chamber, Lines, Septic Tank , STP)100%
Solid Waste Management And Disposal
Storm Water Drains50%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply100%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.