📞 +91 98200 30685✉️
RERA: A51800043517

Golden City Complex

by Shree J.P. Builders Partnership
Certificate SignedP51700006780

Project Information

RERA Certificate No.
P51700006780
Registration No.
REA51700015781
Registration Date
2021-09-10
Developer
Shree J.P. Builders Partnership
Architect
B A C Planners And Engineers Pvt Ltd
Project Bank
IDBI BANK
Proposed Possession
2021-12-30
Revised Possession
2021-12-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
4
Project Area
5160.00 sq.m
Total FSI
4595.51
Approved FSI
4595.51
MahaRERA QR
Golden City Complex
MahaRERA — P51700006780
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors9
Sanctioned9
🅿️Closed Parking1
📅Completion2020-12-31
🏗️Proposed Floors9
Sanctioned9
🅿️Closed Parking1
📅Completion2020-12-31
🏗️Proposed Floors15
Sanctioned15
🅿️Closed Parking7
📅Completion2020-12-31
🏗️Proposed Floors9
Sanctioned9
🅿️Closed Parking1
📅Completion2020-12-31

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
First Floor Resident33.43000030517578000
0%
First Floor Resident33.61000061035156000
0%
First Floor Resident53.599998474121094000
0%
First Floor Shop14.390000343322754000
0%
First Floor Shop16.440000534057617000
0%
First Floor Shop17.469999313354492000
0%
First Floor Shop18.84000015258789000
0%
First Floor Shop20.889999389648438000
0%
Ground Floor Shop14.390000343322754000
0%
Ground Floor Shop16.440000534057617000
0%
Ground Floor Shop17.469999313354492000
0%
Ground Floor Shop18.84000015258789000
0%
Ground Floor Shop20.889999389648438000
0%
Residential27.899999618530273000
0%
Residential33.43000030517578000
0%
Residential33.58000183105469000
0%
Residential33.61000061035156000
0%
Residential33.880001068115234000
0%
Residential34.29999923706055000
0%
Residential34.939998626708984000
0%
Residential36.66999816894531000
0%
Residential36.959999084472656000
0%
Residential37.54999923706055000
0%
Residential47.5099983215332000
0%
Residential49.88999938964844000
0%
Residential51.220001220703125000
0%
Residential53.36000061035156000
0%
Residential53.599998474121094000
0%
Residential54.02000045776367000
0%
Residential54.20000076293945000
0%
Residential54.22999954223633000
0%
Residential54.619998931884766000
0%

D - Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
RESIDENTIAL33.88770
100%
RESIDENTIAL34.3761
86%
RESIDENTIAL34.94734
43%
RESIDENTIAL36.96110
100%
RESIDENTIAL37.55101
0%

Wing - A

TypeCarpet (sq.ft)TotalBookedAvailableStatus
FIRST FLOOR RESIDENT33.43211
50%
FIRST FLOOR RESIDENT33.61110
100%
FIRST FLOOR RESIDENT53.6101
0%
FIRST FLOOR SHOP14.39321
67%
FIRST FLOOR SHOP16.44202
0%
FIRST FLOOR SHOP17.47110
100%
FIRST FLOOR SHOP18.84413
25%
FIRST FLOOR SHOP20.89110
100%
GROUND FLOOR SHOP14.39312
33%
GROUND FLOOR SHOP16.44220
100%
GROUND FLOOR SHOP17.47110
100%
GROUND FLOOR SHOP18.84440
100%
GROUND FLOOR SHOP20.89110
100%
RESIDENTIAL33.4312102
83%
RESIDENTIAL33.61660
100%
RESIDENTIAL53.6642
67%
RESIDENTIAL54.621266
50%

Wing - B

TypeCarpet (sq.ft)TotalBookedAvailableStatus
RESIDENTIAL27.9761
86%
RESIDENTIAL47.51826
25%
RESIDENTIAL49.89817
12%
RESIDENTIAL51.22826
25%
RESIDENTIAL54.21688
50%

Wing - C

TypeCarpet (sq.ft)TotalBookedAvailableStatus
RESIDENTIAL33.58770
100%
RESIDENTIAL33.88770
100%
RESIDENTIAL36.67101
0%
RESIDENTIAL53.36761
86%
RESIDENTIAL54.02770
100%
RESIDENTIAL54.23761
86%

Construction Progress

D - WING

Basement (if any)100%

D - Wing

Excavation100%

D - WING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

D - Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

D - WING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

D - Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

D - WING

Plinth100%
Podiums (if any) 0%

D - Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

D - WING

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

D - Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

D - WING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

D - Wing

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

WING - A

Basement (if any)100%

Wing - A

Excavation100%

WING - A

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Wing - A

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

WING - A

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%

Wing - A

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises80%
Overall Percentage of Completion of the work done For the entire Building /Wing56%

WING - A

Plinth100%
Podiums (if any) 0%

Wing - A

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

WING - A

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%

Wing - A

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING - A

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing - A

Stilt Floor80%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

WING - B

Basement (if any)100%

Wing - B

Excavation100%

WING - B

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Wing - B

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

WING - B

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%

Wing - B

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises60%
Overall Percentage of Completion of the work done For the entire Building /Wing48%

WING - B

Plinth100%
Podiums (if any) 0%

Wing - B

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

WING - B

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%

Wing - B

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.60%

WING - B

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%

Wing - B

Stilt Floor60%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

WING - C

Basement (if any)100%

Wing - C

Excavation100%

WING - C

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing - C

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

WING - C

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing - C

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

WING - C

Plinth100%
Podiums (if any) 0%

Wing - C

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

WING - C

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Wing - C

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING - C

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing - C

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station80%
Energy management100%
Fire Protection And Fire Safety Requirements80%
Landscaping & Tree Planting70%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)100%
Solid Waste Management And Disposal
Storm Water Drains80%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water70%
Water Conservation, Rain water Harvesting100%
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.