Sai Sansar Residency

by Arun Patil
Kept in AbeyanceP51700008197

Project Information

RERA Certificate No.
P51700008197
Registration No.
REA51700010407
Developer
Arun Patil
Architect
Kedar Vijay Kale
Project Bank
STATE BANK OF INDIA
Proposed Possession
2020-12-31
Revised Possession
2021-06-30
Extended Possession
2022-12-30
Buildings
2
Project Area
7210.00 sq.m
Total FSI
7676.22
MahaRERA QR
Sai Sansar Residency
MahaRERA — P51700008197
Scan to verify on MahaRERA portal

Wing-wise Details

🅿️Closed Parking13
📅Completion2020-12-31
🅿️Closed Parking26
📅Completion2020-12-31

Apartment Configurations

Building No 4

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK33.3614140
100%
2 BHK50.78770
100%
2 BHK52.58770
100%

Building No 6

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK30.8821201
95%
1 BHK31.9714140
100%
1 BHK32.4114131
93%
2 BHK46.4814122
86%

Construction Progress

Building No 4

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

Building No 6

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate80%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises95%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space80%
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station90%
Energy management
Fire Protection And Fire Safety Requirements100%
Landscaping & Tree Planting90%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)100%
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting90%
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting100%
Water Supply100%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.