📞 +91 98200 30685✉️
RERA: A51800043517

Hari Krupa Residency, Kharde, Shahapur

by Harikrupa Buildcon Llp
Kept in AbeyanceP51700010244

Project Information

RERA Certificate No.
P51700010244
Registration No.
REA51700019454
Developer
Harikrupa Buildcon Llp
Project Bank
Sarswat Bank
Proposed Possession
2022-07-31
Revised Possession
2023-07-31
Extended Possession
1900-01-01
Buildings
3
Project Area
2514.00 sq.m
Total FSI
2674.19
MahaRERA QR
Hari Krupa Residency, Kharde, Shahapur
MahaRERA — P51700010244
Scan to verify on MahaRERA portal

Wing-wise Details

🚗Open Parking9
🅿️Closed Parking3
📅Completion2022-07-31
🚗Open Parking9
🅿️Closed Parking3
📅Completion2022-07-31
📅Completion2022-07-31

Apartment Configurations

A Type Building Wing-A

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK34.2505
0%
1 BHK34.73101
0%
1 BHK35.86808
0%
2 BHK38.74431
75%
Shop15.05110
100%
SHOP115.05101
0%
SHOP213.01101
0%
SHOP314.31110
100%
SHOP48.45101
0%
SHOP514.31101
0%
SHOP613.01101
0%

A Type Building Wing-B

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK20.09808
0%
1 BHK23.21101
0%
1 BHK25.85505
0%
1 BHK26.49404
0%
1 BHK26.53404
0%
1 BHK32.71808
0%
1 BHK35.83101
0%
1RK17.24505
0%
1RK17.5505
0%
1RK19.42404
0%
SHOP114.43101
0%
SHOP212.43101
0%
SHOP315.04505
0%
SHOP412.95202
0%
SHOP510.26101
0%
SHOP612.57202
0%
SHOP79.16101
0%

D Type Wing -C

TypeCarpet (sq.ft)TotalBookedAvailableStatus
NIL000
0%

Construction Progress

A Type Building Wing-A

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

A Type Building Wing-B

Excavation0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

D Type Wing -C

Excavation0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting40%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)40%
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.