RERA: A51800043517

Manohar Shreeji Nirvana Phase 4

by Deeplaxmi Developers Partnership
Certificate SignedP51700015978

Project Information

RERA Certificate No.
P51700015978
Registration No.
REA51700034424
Registration Date
2021-09-10
Developer
Deeplaxmi Developers Partnership
Architect
Urban Architects
Project Bank
KOTAK MAHINDRA BANK LIMITED
Proposed Possession
2022-10-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
11
Project Area
6702.00 sq.m
Total FSI
9227.48
Approved FSI
9227.48
MahaRERA QR
Manohar Shreeji Nirvana Phase 4
MahaRERA — P51700015978
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors5
Sanctioned5
📅Completion2021-10-31
🏗️Proposed Floors5
Sanctioned5
📅Completion2021-10-31
🏗️Proposed Floors5
Sanctioned5
📅Completion2021-10-31
🏗️Proposed Floors5
Sanctioned5
📅Completion2021-10-31
🏗️Proposed Floors5
Sanctioned5
📅Completion2021-10-31
🏗️Proposed Floors5
Sanctioned5
📅Completion2021-10-31
🏗️Proposed Floors5
Sanctioned5
📅Completion2021-10-31
🏗️Proposed Floors5
Sanctioned5
📅Completion2021-10-31
🏗️Proposed Floors5
Sanctioned5
📅Completion2021-10-31
🏗️Proposed Floors5
Sanctioned5
📅Completion2021-10-31
🏗️Proposed Floors5
Sanctioned5
📅Completion2021-10-31

Apartment Configurations

Building No A

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK31.44101
0%
1 BHK31.69826
25%
2 BHK39.98110
100%
2 BHK41.37413
25%
2 BHK43.47523
40%

Building No B

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK31.58202
0%
1 BHK31.981248
33%
2 BHK40.97101
0%
2 BHK41.37422
50%

Building No C

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK31.58220
100%
1 BHK31.981275
58%
2 BHK40.97110
100%
2 BHK41.34422
50%

Building No D

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK30.88110
100%
1 BHK32.01853
62%
2 BHK40.26110
100%
2 BHK41.34431
75%
2 BHK43.47523
40%

Building No E

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK30.87110
100%
1 BHK31.98853
62%
2 BHK40.26101
0%
2 BHK41.34422
50%
2 BHK43.73532
60%

Building No H

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK31.15211
50%
1 BHK31.96844
50%
1 BHK33.16110
100%
1 BHK33.47835
38%
2 BHK41.32110
100%
2 BHK41.37422
50%
2 BHK44.3532
60%

Building No I

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK31.58211
50%
1 BHK31.981275
58%
2 BHK40.97101
0%
2 BHK41.37422
50%

Building No J

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK31.43202
0%
1 BHK32.01275
58%
2 BHK40.82101
0%
2 BHK42.47422
50%

Building No K

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK31.44211
50%
1 BHK32.01275
58%
2 BHK40.82110
100%
2 BHK42.47431
75%

Building No L

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK31.44202
0%
1 BHK31.981257
42%
2 BHK40.82101
0%
2 BHK41.37413
25%

Building No M

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK30.88101
0%
1 BHK31.98844
50%
2 BHK40.26101
0%
2 BHK41.34422
50%
2 BHK43.47523
40%

Construction Progress

BUILDING NO A

Basement (if any)100%

Building No A

Excavation100%

BUILDING NO A

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Building No A

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

BUILDING NO A

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Building No A

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

BUILDING NO A

Plinth100%
Podiums (if any) 0%

Building No A

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

BUILDING NO A

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Building No A

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

BUILDING NO A

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Building No A

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

BUILDING NO B

Basement (if any)100%

Building No B

Excavation100%

BUILDING NO B

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Building No B

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

BUILDING NO B

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Building No B

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

BUILDING NO B

Plinth100%
Podiums (if any) 0%

Building No B

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

BUILDING NO B

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Building No B

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

BUILDING NO B

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Building No B

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

BUILDING NO C

Basement (if any)100%

Building No C

Excavation100%

BUILDING NO C

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Building No C

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

BUILDING NO C

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Building No C

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

BUILDING NO C

Plinth100%
Podiums (if any) 0%

Building No C

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

BUILDING NO C

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Building No C

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

BUILDING NO C

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Building No C

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

BUILDING NO D

Basement (if any)100%

Building No D

Excavation100%

BUILDING NO D

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Building No D

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

BUILDING NO D

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Building No D

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

BUILDING NO D

Plinth100%
Podiums (if any) 0%

Building No D

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

BUILDING NO D

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Building No D

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

BUILDING NO D

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Building No D

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

BUILDING NO E

Basement (if any)100%

Building No E

Excavation100%

BUILDING NO E

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Building No E

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

BUILDING NO E

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Building No E

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

BUILDING NO E

Plinth100%
Podiums (if any) 0%

Building No E

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

BUILDING NO E

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Building No E

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

BUILDING NO E

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Building No E

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

BUILDING NO H

Basement (if any)100%

Building No H

Excavation100%

BUILDING NO H

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Building No H

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

BUILDING NO H

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Building No H

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

BUILDING NO H

Plinth100%
Podiums (if any) 0%

Building No H

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

BUILDING NO H

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Building No H

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

BUILDING NO H

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Building No H

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

BUILDING NO I

Basement (if any)100%

Building No I

Excavation100%

BUILDING NO I

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Building No I

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

BUILDING NO I

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Building No I

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

BUILDING NO I

Plinth100%
Podiums (if any) 0%

Building No I

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

BUILDING NO I

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Building No I

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

BUILDING NO I

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Building No I

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

BUILDING NO J

Basement (if any)100%

Building No J

Excavation100%

BUILDING NO J

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Building No J

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

BUILDING NO J

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Building No J

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

BUILDING NO J

Plinth100%
Podiums (if any) 0%

Building No J

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

BUILDING NO J

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Building No J

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

BUILDING NO J

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Building No J

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

BUILDING NO K

Basement (if any)100%

Building No K

Excavation100%

BUILDING NO K

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Building No K

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

BUILDING NO K

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Building No K

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

BUILDING NO K

Plinth100%
Podiums (if any) 0%

Building No K

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

BUILDING NO K

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Building No K

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

BUILDING NO K

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Building No K

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

BUILDING NO L

Basement (if any)100%

Building No L

Excavation100%

BUILDING NO L

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Building No L

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

BUILDING NO L

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Building No L

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

BUILDING NO L

Plinth100%
Podiums (if any) 0%

Building No L

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

BUILDING NO L

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Building No L

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

BUILDING NO L

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Building No L

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

BUILDING NO M

Basement (if any)100%

Building No M

Excavation100%

BUILDING NO M

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Building No M

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

BUILDING NO M

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Building No M

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

BUILDING NO M

Plinth100%
Podiums (if any) 0%

Building No M

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

BUILDING NO M

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Building No M

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

BUILDING NO M

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Building No M

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly