📞 +91 98200 30685✉️
RERA: A51800043517

Tiara

by Sagar Enterprise Partnership
Certificate SignedP51700020733

Project Information

RERA Certificate No.
P51700020733
Registration No.
REA51700056048
Registration Date
2024-06-26
Developer
Sagar Enterprise Partnership
Project Bank
HDFC BANK
Proposed Possession
2024-03-30
Revised Possession
1900-01-01
Extended Possession
2025-03-30
Units Sold
0
Buildings
2
Project Area
4078.00 sq.m
Total FSI
7254.50
Approved FSI
3272.95
MahaRERA QR
Tiara
MahaRERA — P51700020733
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors23
Sanctioned23
🚗Open Parking8
🅿️Closed Parking67
📅Completion2023-03-31
🏗️Proposed Floors23
Sanctioned23
🚗Open Parking8
🅿️Closed Parking67
📅Completion2023-03-31

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1Bhk32.15999984741211000
0%
1Bhk32.459999084472656000
0%
1Bhk37.630001068115234000
0%
1Bhk37.66999816894531000
0%
1Bhk37.790000915527344000
0%
1Bhk37.81999969482422000
0%
1Bhk37.83000183105469000
0%
1Bhk43.83000183105469000
0%
1Bhk43.849998474121094000
0%
2Bhk43.83000183105469000
0%
2Bhk46.939998626708984000
0%
2Bhk46.959999084472656000
0%
2Bhk48.36000061035156000
0%

Tiara A Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK32.16321
67%
1 BHK32.46321
67%
1 BHK37.79322210
69%
1 BHK37.8235287
80%
2 BHK43.83110
100%
2 BHK46.9618612
33%
2 BHK48.3617143
82%

Tiara B Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK32.1626188
69%
1 BHK32.4626188
69%
1 BHK37.63532
60%
1 BHK37.67651
83%
1 BHK37.8311101
91%
1 BHK43.831385
62%
1 BHK43.8513112
85%
2 BHK46.94651
83%
2 BHK46.96624
33%

Construction Progress

TIARA A WING

Basement (if any)100%

Tiara A Wing

Excavation100%

TIARA A WING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Tiara A Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

TIARA A WING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Tiara A Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing100%

TIARA A WING

Plinth100%
Podiums (if any) 100%

Tiara A Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

TIARA A WING

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Tiara A Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

TIARA A WING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Tiara A Wing

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

TIARA B WING

Basement (if any)100%

Tiara B Wing

Excavation100%

TIARA B WING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Tiara B Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

TIARA B WING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Tiara B Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing100%

TIARA B WING

Plinth100%
Podiums (if any) 100%

Tiara B Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

TIARA B WING

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Tiara B Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

TIARA B WING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Tiara B Wing

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space100%
Community Buildings100%
Electrical Meter Room, Sub-Station, Receiving Station100%
Energy management100%
Fire Protection And Fire Safety Requirements100%
Landscaping & Tree Planting100%
Open Parking100%
Sewerage (Chamber, Lines, Septic Tank , STP)100%
Solid Waste Management And Disposal100%
Storm Water Drains100%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting100%
Water Supply100%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.