SHALIMAR CO.OP HSG SOC LTD

by NEENA SHAILESH PARANJAPE Individual
Certificate SignedP51700027861

Project Information

RERA Certificate No.
P51700027861
Registration No.
REA51700081206
Registration Date
2021-09-09
Developer
NEENA SHAILESH PARANJAPE Individual
Architect
Anil Jagwani
Project Bank
CANARA BANK
Proposed Possession
2024-04-30
Revised Possession
1900-01-01
Extended Possession
2026-05-31
Units Sold
0
Buildings
1
Project Area
914.25 sq.m
Total FSI
2166.82
Approved FSI
2166.82
MahaRERA QR
SHALIMAR CO.OP HSG SOC LTD
MahaRERA — P51700027861
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors14
Sanctioned14
🚗Open Parking3
📅Completion2023-10-31

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3Bhk1751.31005859375000
0%
Shop214.55999755859375000
0%

Shalimar Co Op Hsg Soc Ltd

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3 BHK1751.3126188
69%
Shop214.561192
82%

Construction Progress

SHALIMAR CO OP HSG SOC LTD

Basement (if any)100%

Shalimar Co Op Hsg Soc Ltd

Excavation100%

SHALIMAR CO OP HSG SOC LTD

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Shalimar Co Op Hsg Soc Ltd

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

SHALIMAR CO OP HSG SOC LTD

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%

Shalimar Co Op Hsg Soc Ltd

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises20%
Overall Percentage of Completion of the work done For the entire Building /Wing32%

SHALIMAR CO OP HSG SOC LTD

Plinth100%
Podiums (if any) 0%

Shalimar Co Op Hsg Soc Ltd

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

SHALIMAR CO OP HSG SOC LTD

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure85%

Shalimar Co Op Hsg Soc Ltd

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

SHALIMAR CO OP HSG SOC LTD

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Shalimar Co Op Hsg Soc Ltd

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.