Madhusudan Retreat

by Madhusudan Leisure Homes Others
Certificate SignedP51700030973

Project Information

RERA Certificate No.
P51700030973
Registration No.
REA51700092390
Registration Date
2025-10-03
Developer
Madhusudan Leisure Homes Others
Architect
Ashish Agarwal
Project Bank
HDFC BANK
Proposed Possession
2024-06-30
Revised Possession
1900-01-01
Extended Possession
2025-06-29
Total Units
106
Units Sold
52 (49%)
Buildings
53
Project Area
9822.95 sq.m
Total FSI
14734.43
Approved FSI
14734.43
MahaRERA QR
Madhusudan Retreat
MahaRERA — P51700030973
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2024-06-30

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow No 10185.19999694824219000
0%
Bungalow No 10259.84000015258789000
0%
Bungalow No 10359.84000015258789000
0%
Bungalow No 10459.84000015258789000
0%
Bungalow No 10559.84000015258789000
0%
Bungalow No 10659.84000015258789000
0%
Bungalow No 10759.84000015258789000
0%
Bungalow No 10859.84000015258789000
0%
Bungalow No 10959.84000015258789000
0%
Bungalow No 11059.84000015258789000
0%
Bungalow No 13285.19999694824219000
0%
Bungalow No 13385.19999694824219000
0%
Bungalow No 359.84000015258789000
0%
Bungalow No 3059.84000015258789000
0%
Bungalow No 3185.19999694824219000
0%
Bungalow No 3285.19999694824219000
0%
Bungalow No 3385.19999694824219000
0%
Bungalow No 3485.19999694824219000
0%
Bungalow No 3585.19999694824219000
0%
Bungalow No 3685.19999694824219000
0%
Bungalow No 3785.19999694824219000
0%
Bungalow No 3885.19999694824219000
0%
Bungalow No 3985.19999694824219000
0%
Bungalow No 4121.5000
0%
Bungalow No 4059.84000015258789000
0%
Bungalow No 4185.19999694824219000
0%
Bungalow No 42121.5000
0%
Bungalow No 4385.19999694824219000
0%
Bungalow No 585.19999694824219000
0%
Bungalow No 6121.5000
0%
Bungalow No 6259.84000015258789000
0%
Bungalow No 6359.84000015258789000
0%
Bungalow No 6459.84000015258789000
0%
Bungalow No 6559.84000015258789000
0%
Bungalow No 6659.84000015258789000
0%
Bungalow No 6759.84000015258789000
0%
Bungalow No 6859.84000015258789000
0%
Bungalow No 6959.84000015258789000
0%
Bungalow No 7121.5000
0%
Bungalow No 7059.84000015258789000
0%
Bungalow No 7185.19999694824219000
0%
Bungalow No 7285.19999694824219000
0%
Bungalow No 7385.19999694824219000
0%
Bungalow No 7459.63999938964844000
0%
Bungalow No 7559.84000015258789000
0%
Bungalow No 7659.84000015258789000
0%
Bungalow No 7759.84000015258789000
0%
Bungalow No 7859.84000015258789000
0%
Bungalow No 7985.19999694824219000
0%
Bungalow No 8085.19999694824219000
0%
Bungalow No 8185.19999694824219000
0%
Bungalow No 8385.19999694824219000
0%
Bungalow No 8485.19999694824219000
0%

Bungalow No 101

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 10185.2101
0%

Bungalow No 102

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 10259.84101
0%

Bungalow No 103

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 10359.84101
0%

Bungalow No 104

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 10459.84101
0%

Bungalow No 105

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 10559.84101
0%

Bungalow No 106

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 10659.84101
0%

Bungalow No 107

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 10759.84101
0%

Bungalow No 108

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 10859.84101
0%

Bungalow No 109

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 10959.84101
0%

Bungalow No 110

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 11059.84101
0%

Bungalow No 132

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 13285.2101
0%

Bungalow No 133

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 13385.2101
0%

Bungalow No 3

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 359.84101
0%

Bungalow No 30

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 3059.84101
0%

Bungalow No 31

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 3185.2101
0%

Bungalow No 32

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 3285.2101
0%

Bungalow No 33

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 3385.2101
0%

Bungalow No 34

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 3485.2101
0%

Bungalow No 35

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 3585.2101
0%

Bungalow No 36

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 3685.2101
0%

Bungalow No 37

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 3785.2101
0%

Bungalow No 38

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 3885.2101
0%

Bungalow No 39

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 3985.2101
0%

Bungalow No 4

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 4121.5101
0%

Bungalow No 40

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 4059.84101
0%

Bungalow No 41

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 4185.2101
0%

Bungalow No 42

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 42121.5101
0%

Bungalow No 43

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 4385.2101
0%

Bungalow No 5

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 585.2101
0%

Bungalow No 6

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 6121.5101
0%

Bungalow No 62

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 6259.84101
0%

Bungalow No 63

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 6359.84101
0%

Bungalow No 64

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 6459.84101
0%

Bungalow No 65

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 6559.84101
0%

Bungalow No 66

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 6659.84101
0%

Bungalow No 67

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 6759.84101
0%

Bungalow No 68

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 6859.84101
0%

Bungalow No 69

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 6959.84101
0%

Bungalow No 7

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 7121.5101
0%

Bungalow No 70

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 7059.84101
0%

Bungalow No 71

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 7185.2101
0%

Bungalow No 72

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 7285.2101
0%

Bungalow No 73

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 7385.2101
0%

Bungalow No 74

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 7459.64101
0%

Bungalow No 75

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 7559.84101
0%

Bungalow No 76

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 7659.84101
0%

Bungalow No 77

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 7759.84101
0%

Bungalow No 78

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 7859.84101
0%

Bungalow No 79

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 7985.2101
0%

Bungalow No 80

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 8085.2101
0%

Bungalow No 81

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 8185.2101
0%

Bungalow No 83

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 8385.2101
0%

Bungalow No 84

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BUNGALOW NO 8485.2101
0%

Construction Progress

BUNGALOW NO 101

Basement (if any)0%

Bungalow No 101

Excavation0%

BUNGALOW NO 101

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 101

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 101

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 101

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%

BUNGALOW NO 101

Plinth0%
Podiums (if any) 0%

Bungalow No 101

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 101

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 101

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 101

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 101

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 102

Basement (if any)100%

Bungalow No 102

Excavation100%

BUNGALOW NO 102

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 102

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 102

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 102

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing20%

BUNGALOW NO 102

Plinth100%
Podiums (if any) 0%

Bungalow No 102

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 102

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 102

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 102

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 102

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 103

Basement (if any)0%

Bungalow No 103

Excavation100%

BUNGALOW NO 103

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 103

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 103

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 103

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing10%

BUNGALOW NO 103

Plinth0%
Podiums (if any) 0%

Bungalow No 103

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 103

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 103

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 103

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 103

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 104

Basement (if any)100%

Bungalow No 104

Excavation100%

BUNGALOW NO 104

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 104

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 104

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 104

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing25%

BUNGALOW NO 104

Plinth100%
Podiums (if any) 0%

Bungalow No 104

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 104

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure50%

Bungalow No 104

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 104

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 104

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure50%

BUNGALOW NO 105

Basement (if any)0%

Bungalow No 105

Excavation100%

BUNGALOW NO 105

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 105

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 105

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 105

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing10%

BUNGALOW NO 105

Plinth0%
Podiums (if any) 0%

Bungalow No 105

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 105

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 105

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 105

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 105

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 106

Basement (if any)0%

Bungalow No 106

Excavation100%

BUNGALOW NO 106

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 106

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 106

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 106

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing10%

BUNGALOW NO 106

Plinth0%
Podiums (if any) 0%

Bungalow No 106

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 106

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 106

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 106

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 106

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 107

Basement (if any)0%

Bungalow No 107

Excavation100%

BUNGALOW NO 107

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 107

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 107

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 107

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing10%

BUNGALOW NO 107

Plinth0%
Podiums (if any) 0%

Bungalow No 107

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 107

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 107

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 107

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 107

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 108

Basement (if any)0%

Bungalow No 108

Excavation100%

BUNGALOW NO 108

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 108

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 108

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 108

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing10%

BUNGALOW NO 108

Plinth0%
Podiums (if any) 0%

Bungalow No 108

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 108

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 108

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 108

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 108

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 109

Basement (if any)100%

Bungalow No 109

Excavation100%

BUNGALOW NO 109

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 109

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 109

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 109

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing20%

BUNGALOW NO 109

Plinth100%
Podiums (if any) 0%

Bungalow No 109

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 109

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 109

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 109

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 109

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 110

Basement (if any)100%

Bungalow No 110

Excavation100%

BUNGALOW NO 110

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 110

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 110

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 110

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing20%

BUNGALOW NO 110

Plinth100%
Podiums (if any) 0%

Bungalow No 110

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 110

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 110

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 110

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 110

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 132

Basement (if any)100%

Bungalow No 132

Excavation100%

BUNGALOW NO 132

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 132

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 132

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 132

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing25%

BUNGALOW NO 132

Plinth100%
Podiums (if any) 0%

Bungalow No 132

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 132

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure50%

Bungalow No 132

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 132

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 132

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure50%

BUNGALOW NO 133

Basement (if any)100%

Bungalow No 133

Excavation100%

BUNGALOW NO 133

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 133

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 133

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 133

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing30%

BUNGALOW NO 133

Plinth100%
Podiums (if any) 0%

Bungalow No 133

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 133

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%

Bungalow No 133

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 133

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 133

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

BUNGALOW NO 3

Basement (if any)0%

Bungalow No 3

Excavation100%

BUNGALOW NO 3

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 3

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 3

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 3

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing10%

BUNGALOW NO 3

Plinth0%
Podiums (if any) 0%

Bungalow No 3

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 3

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 3

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 3

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 3

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 30

Basement (if any)0%

Bungalow No 30

Excavation100%

BUNGALOW NO 30

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 30

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 30

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 30

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing10%

BUNGALOW NO 30

Plinth0%
Podiums (if any) 0%

Bungalow No 30

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 30

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 30

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 30

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 30

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 31

Basement (if any)0%

Bungalow No 31

Excavation100%

BUNGALOW NO 31

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 31

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 31

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 31

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing10%

BUNGALOW NO 31

Plinth0%
Podiums (if any) 0%

Bungalow No 31

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 31

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 31

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 31

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 31

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 32

Basement (if any)0%

Bungalow No 32

Excavation100%

BUNGALOW NO 32

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 32

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 32

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 32

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing10%

BUNGALOW NO 32

Plinth0%
Podiums (if any) 0%

Bungalow No 32

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 32

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 32

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 32

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 32

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 33

Basement (if any)0%

Bungalow No 33

Excavation100%

BUNGALOW NO 33

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 33

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 33

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 33

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing10%

BUNGALOW NO 33

Plinth0%
Podiums (if any) 0%

Bungalow No 33

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 33

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 33

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 33

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 33

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 34

Basement (if any)0%

Bungalow No 34

Excavation100%

BUNGALOW NO 34

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 34

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 34

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 34

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing10%

BUNGALOW NO 34

Plinth0%
Podiums (if any) 0%

Bungalow No 34

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 34

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 34

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 34

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 34

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 35

Basement (if any)100%

Bungalow No 35

Excavation100%

BUNGALOW NO 35

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 35

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 35

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 35

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing20%

BUNGALOW NO 35

Plinth100%
Podiums (if any) 0%

Bungalow No 35

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 35

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 35

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 35

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 35

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 36

Basement (if any)100%

Bungalow No 36

Excavation100%

BUNGALOW NO 36

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 36

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 36

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 36

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing20%

BUNGALOW NO 36

Plinth100%
Podiums (if any) 0%

Bungalow No 36

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 36

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 36

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 36

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 36

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 37

Basement (if any)100%

Bungalow No 37

Excavation100%

BUNGALOW NO 37

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 37

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 37

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 37

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing20%

BUNGALOW NO 37

Plinth100%
Podiums (if any) 0%

Bungalow No 37

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 37

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 37

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 37

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 37

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 38

Basement (if any)100%

Bungalow No 38

Excavation100%

BUNGALOW NO 38

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 38

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 38

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 38

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing25%

BUNGALOW NO 38

Plinth100%
Podiums (if any) 0%

Bungalow No 38

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 38

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure50%

Bungalow No 38

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 38

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 38

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure50%

BUNGALOW NO 39

Basement (if any)100%

Bungalow No 39

Excavation100%

BUNGALOW NO 39

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 39

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 39

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 39

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing20%

BUNGALOW NO 39

Plinth100%
Podiums (if any) 0%

Bungalow No 39

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 39

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 39

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 39

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 39

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 4

Basement (if any)0%

Bungalow No 4

Excavation0%

BUNGALOW NO 4

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 4

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 4

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 4

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%

BUNGALOW NO 4

Plinth0%
Podiums (if any) 0%

Bungalow No 4

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 4

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 4

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 4

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 4

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 40

Basement (if any)100%

Bungalow No 40

Excavation100%

BUNGALOW NO 40

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 40

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 40

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 40

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing20%

BUNGALOW NO 40

Plinth100%
Podiums (if any) 0%

Bungalow No 40

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 40

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 40

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 40

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 40

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 41

Basement (if any)100%

Bungalow No 41

Excavation100%

BUNGALOW NO 41

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 41

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 41

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 41

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing20%

BUNGALOW NO 41

Plinth100%
Podiums (if any) 0%

Bungalow No 41

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 41

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 41

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 41

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 41

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 42

Basement (if any)0%

Bungalow No 42

Excavation0%

BUNGALOW NO 42

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 42

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 42

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 42

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%

BUNGALOW NO 42

Plinth0%
Podiums (if any) 0%

Bungalow No 42

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 42

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 42

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 42

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 42

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 43

Basement (if any)100%

Bungalow No 43

Excavation100%

BUNGALOW NO 43

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 43

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 43

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 43

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing25%

BUNGALOW NO 43

Plinth100%
Podiums (if any) 0%

Bungalow No 43

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 43

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure50%

Bungalow No 43

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 43

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 43

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure50%

BUNGALOW NO 5

Basement (if any)100%

Bungalow No 5

Excavation100%

BUNGALOW NO 5

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 5

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 5

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 5

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing20%

BUNGALOW NO 5

Plinth100%
Podiums (if any) 0%

Bungalow No 5

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 5

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 5

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 5

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 5

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 6

Basement (if any)0%

Bungalow No 6

Excavation0%

BUNGALOW NO 6

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 6

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 6

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 6

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%

BUNGALOW NO 6

Plinth0%
Podiums (if any) 0%

Bungalow No 6

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 6

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 6

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 6

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 6

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 62

Basement (if any)0%

Bungalow No 62

Excavation100%

BUNGALOW NO 62

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 62

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 62

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 62

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing10%

BUNGALOW NO 62

Plinth0%
Podiums (if any) 0%

Bungalow No 62

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 62

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 62

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 62

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 62

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 63

Basement (if any)0%

Bungalow No 63

Excavation100%

BUNGALOW NO 63

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 63

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 63

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 63

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing10%

BUNGALOW NO 63

Plinth0%
Podiums (if any) 0%

Bungalow No 63

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 63

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 63

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 63

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 63

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 64

Basement (if any)0%

Bungalow No 64

Excavation100%

BUNGALOW NO 64

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 64

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 64

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 64

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing10%

BUNGALOW NO 64

Plinth0%
Podiums (if any) 0%

Bungalow No 64

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 64

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 64

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 64

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 64

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 65

Basement (if any)0%

Bungalow No 65

Excavation100%

BUNGALOW NO 65

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 65

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 65

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 65

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing10%

BUNGALOW NO 65

Plinth0%
Podiums (if any) 0%

Bungalow No 65

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 65

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 65

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 65

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 65

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 66

Basement (if any)0%

Bungalow No 66

Excavation100%

BUNGALOW NO 66

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 66

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 66

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 66

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing10%

BUNGALOW NO 66

Plinth0%
Podiums (if any) 0%

Bungalow No 66

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 66

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 66

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 66

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 66

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 67

Basement (if any)0%

Bungalow No 67

Excavation100%

BUNGALOW NO 67

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 67

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 67

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 67

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing10%

BUNGALOW NO 67

Plinth0%
Podiums (if any) 0%

Bungalow No 67

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 67

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 67

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 67

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 67

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 68

Basement (if any)0%

Bungalow No 68

Excavation100%

BUNGALOW NO 68

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 68

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 68

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 68

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing10%

BUNGALOW NO 68

Plinth0%
Podiums (if any) 0%

Bungalow No 68

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 68

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 68

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 68

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 68

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 69

Basement (if any)0%

Bungalow No 69

Excavation100%

BUNGALOW NO 69

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 69

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 69

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 69

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing10%

BUNGALOW NO 69

Plinth0%
Podiums (if any) 0%

Bungalow No 69

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 69

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 69

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 69

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 69

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 7

Basement (if any)0%

Bungalow No 7

Excavation100%

BUNGALOW NO 7

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 7

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 7

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 7

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing10%

BUNGALOW NO 7

Plinth0%
Podiums (if any) 0%

Bungalow No 7

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 7

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 7

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 7

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 7

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 70

Basement (if any)0%

Bungalow No 70

Excavation100%

BUNGALOW NO 70

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 70

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 70

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 70

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing10%

BUNGALOW NO 70

Plinth0%
Podiums (if any) 0%

Bungalow No 70

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 70

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 70

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 70

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 70

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 71

Basement (if any)0%

Bungalow No 71

Excavation100%

BUNGALOW NO 71

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 71

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 71

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 71

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing10%

BUNGALOW NO 71

Plinth0%
Podiums (if any) 0%

Bungalow No 71

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 71

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 71

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 71

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 71

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 72

Basement (if any)100%

Bungalow No 72

Excavation100%

BUNGALOW NO 72

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 72

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 72

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 72

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing20%

BUNGALOW NO 72

Plinth100%
Podiums (if any) 0%

Bungalow No 72

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 72

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 72

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 72

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 72

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 73

Basement (if any)100%

Bungalow No 73

Excavation100%

BUNGALOW NO 73

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 73

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 73

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 73

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing30%

BUNGALOW NO 73

Plinth100%
Podiums (if any) 0%

Bungalow No 73

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 73

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%

Bungalow No 73

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 73

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 73

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

BUNGALOW NO 74

Basement (if any)100%

Bungalow No 74

Excavation100%

BUNGALOW NO 74

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 74

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 74

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 74

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing20%

BUNGALOW NO 74

Plinth100%
Podiums (if any) 0%

Bungalow No 74

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 74

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 74

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 74

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 74

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 75

Basement (if any)100%

Bungalow No 75

Excavation100%

BUNGALOW NO 75

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 75

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 75

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 75

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing20%

BUNGALOW NO 75

Plinth100%
Podiums (if any) 0%

Bungalow No 75

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 75

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 75

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 75

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 75

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 76

Basement (if any)100%

Bungalow No 76

Excavation100%

BUNGALOW NO 76

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 76

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 76

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 76

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing20%

BUNGALOW NO 76

Plinth100%
Podiums (if any) 0%

Bungalow No 76

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 76

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 76

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 76

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 76

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 77

Basement (if any)100%

Bungalow No 77

Excavation100%

BUNGALOW NO 77

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 77

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 77

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 77

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing25%

BUNGALOW NO 77

Plinth100%
Podiums (if any) 0%

Bungalow No 77

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 77

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure50%

Bungalow No 77

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 77

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 77

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure50%

BUNGALOW NO 78

Basement (if any)100%

Bungalow No 78

Excavation100%

BUNGALOW NO 78

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 78

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 78

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 78

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing20%

BUNGALOW NO 78

Plinth100%
Podiums (if any) 0%

Bungalow No 78

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 78

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 78

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 78

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 78

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 79

Basement (if any)100%

Bungalow No 79

Excavation100%

BUNGALOW NO 79

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 79

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 79

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 79

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing20%

BUNGALOW NO 79

Plinth100%
Podiums (if any) 0%

Bungalow No 79

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 79

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 79

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 79

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 79

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 80

Basement (if any)0%

Bungalow No 80

Excavation100%

BUNGALOW NO 80

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 80

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 80

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 80

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing10%

BUNGALOW NO 80

Plinth0%
Podiums (if any) 0%

Bungalow No 80

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 80

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 80

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 80

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 80

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 81

Basement (if any)100%

Bungalow No 81

Excavation100%

BUNGALOW NO 81

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 81

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 81

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 81

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing20%

BUNGALOW NO 81

Plinth100%
Podiums (if any) 0%

Bungalow No 81

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 81

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 81

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 81

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 81

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 83

Basement (if any)0%

Bungalow No 83

Excavation100%

BUNGALOW NO 83

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 83

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 83

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 83

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing10%

BUNGALOW NO 83

Plinth0%
Podiums (if any) 0%

Bungalow No 83

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 83

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Bungalow No 83

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 83

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 83

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUNGALOW NO 84

Basement (if any)100%

Bungalow No 84

Excavation100%

BUNGALOW NO 84

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bungalow No 84

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUNGALOW NO 84

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Bungalow No 84

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing25%

BUNGALOW NO 84

Plinth100%
Podiums (if any) 0%

Bungalow No 84

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUNGALOW NO 84

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure50%

Bungalow No 84

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUNGALOW NO 84

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Bungalow No 84

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure50%

NA Plot Without Structure

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 0%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.