📞 +91 98200 30685✉️
RERA: A51800043517

Asha Kiran

by Ashapura Developers Partnership
Certificate SignedP51700033042

Project Information

RERA Certificate No.
P51700033042
Registration No.
REA51700092580
Registration Date
2022-02-03
Developer
Ashapura Developers Partnership
Architect
Joshi Deshware & Associates
Proposed Possession
2023-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
2
Project Area
800.00 sq.m
Total FSI
730.08
Approved FSI
730.08
MahaRERA QR
Asha Kiran
MahaRERA — P51700033042
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors3
Sanctioned3
📅Completion2023-12-31
🏗️Proposed Floors8
Sanctioned8
🚗Open Parking11
🅿️Closed Parking7
📅Completion2023-12-31

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1Bhk27.93000030517578000
0%
1Bhk36.91999816894531000
0%
1Bhk37.13999938964844000
0%
1Bhk37.790000915527344000
0%
1Bhk39.43000030517578000
0%
1Bhk43.209999084472656000
0%
1Bhk44.13999938964844000
0%
2Bhk58.290000915527344000
0%
Shop3.7799999713897705000
0%
Shop7.699999809265137000
0%
Shop9.479999542236328000
0%
Shop14.5000
0%
Shop16.389999389648438000
0%
Shop18.34000015258789000
0%
Shop18.43000030517578000
0%
Shop18.850000381469727000
0%

Building A

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK49.94202
0%
Shop10.81404
0%

Building B

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK20.78303
0%
1 BHK30.4303
0%
1 BHK31.14303
0%
1 BHK33.96303
0%
1 BHK35.15303
0%
Shop17.53404
0%

Construction Progress

Building A

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

Building B

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises85%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.