📞 +91 98200 30685✉️
RERA: A51800043517

Morya Heights

by Morya Developers Partnership
Certificate SignedP51700053294

Project Information

RERA Certificate No.
P51700053294
Registration No.
REA51700142449
Registration Date
2023-11-28
Developer
Morya Developers Partnership
Architect
Mak Design And Co
Project Bank
HDFC BANK
Proposed Possession
2026-06-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
76
Units Sold
18 (24%)
Buildings
1
Project Area
1717.00 sq.m
Total FSI
3855.92
Approved FSI
3855.92
MahaRERA QR
Morya Heights
MahaRERA — P51700053294
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors6
Sanctioned6
🚗Open Parking132
📅Completion2026-06-30

Apartment Configurations

Morya Heights

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK37.36361323
36%
1 BHK38.14615
17%
1 BHK42.58615
17%
1 BHK57.28633
50%
Shop8.93101
0%
Shop9.14101
0%
Shop13.23202
0%

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1Bhk37.36000061035156000
0%
1Bhk38.13999938964844000
0%
1Bhk42.58000183105469000
0%
1Bhk57.279998779296875000
0%
Shop8.930000305175781000
0%
Shop9.140000343322754000
0%
Shop13.229999542236328000
0%

Construction Progress

MORYA HEIGHTS

Basement (if any)100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises25%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%

Morya Heights

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises70%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises25%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.50%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing90%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station70%
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)10%
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply50%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.
👋 Looking for the right project? Let me help you find it!
🏗️
MPE Project Advisor
● Online now