📞 +91 98200 30685✉️
RERA: A51800043517

Vicinia

by Forbes & Company Limited Company
Certificate SignedP51800002564

Project Information

RERA Certificate No.
P51800002564
Registration No.
REA51800008504
Registration Date
2022-07-12
Developer
Forbes & Company Limited Company
Architect
Brighton Architects India Pvt Ltd
Project Bank
AXIS BANK
Proposed Possession
2022-06-30
Revised Possession
2022-06-30
Extended Possession
2023-06-30
Units Sold
0
Buildings
8
Project Area
27263.50 sq.m
Total FSI
60669.00
Approved FSI
31929.05
MahaRERA QR
Vicinia
MahaRERA — P51800002564
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors25
Sanctioned25
⬇️Basements3
🚗Open Parking17
🅿️Closed Parking98
📅Completion2021-06-30
🏗️Proposed Floors25
Sanctioned25
⬇️Basements3
🚗Open Parking17
🅿️Closed Parking98
📅Completion2021-06-30
🏗️Proposed Floors26
Sanctioned26
⬇️Basements3
🚗Open Parking22
🅿️Closed Parking126
📅Completion2021-06-30
🏗️Proposed Floors26
Sanctioned26
⬇️Basements3
🚗Open Parking23
🅿️Closed Parking126
📅Completion2021-06-30
🏗️Proposed Floors26
Sanctioned26
⬇️Basements3
🚗Open Parking26
🅿️Closed Parking145
📅Completion2021-06-30
🏗️Proposed Floors26
Sanctioned26
⬇️Basements3
🚗Open Parking26
🅿️Closed Parking149
📅Completion2021-06-30
🏗️Proposed Floors26
Sanctioned26
⬇️Basements3
🚗Open Parking19
🅿️Closed Parking107
📅Completion2021-06-30
🏗️Proposed Floors26
Sanctioned26
⬇️Basements3
🚗Open Parking19
🅿️Closed Parking106
📅Completion2021-06-30

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Residential38.4900016784668000
0%
Residential62.33000183105469000
0%
Residential77.9800033569336000
0%
Residential89.9000015258789000
0%
Residential94.08999633789062000
0%
Residential94.72000122070312000
0%
Residential95.33999633789062000
0%
Residential106.47000122070312000
0%
Residential140.14999389648438000
0%
Residential140.80999755859375000
0%

Wing A

TypeCarpet (sq.ft)TotalBookedAvailableStatus
RESIDENTIAL140.1534340
100%
RESIDENTIAL140.81660
100%

Wing B

TypeCarpet (sq.ft)TotalBookedAvailableStatus
RESIDENTIAL140.1534340
100%
RESIDENTIAL140.81660
100%

Wing C

TypeCarpet (sq.ft)TotalBookedAvailableStatus
RESIDENTIAL77.9842420
100%
RESIDENTIAL89.921210
100%
RESIDENTIAL94.7218180
100%
RESIDENTIAL95.34330
100%

Wing D

TypeCarpet (sq.ft)TotalBookedAvailableStatus
RESIDENTIAL77.9842420
100%
RESIDENTIAL89.921210
100%
RESIDENTIAL94.7218180
100%
RESIDENTIAL95.34330
100%

Wing E

TypeCarpet (sq.ft)TotalBookedAvailableStatus
RESIDENTIAL38.49202
0%
RESIDENTIAL77.9840400
100%
RESIDENTIAL94.0919172
89%
RESIDENTIAL94.7218171
94%
RESIDENTIAL95.34330
100%

Wing F

TypeCarpet (sq.ft)TotalBookedAvailableStatus
RESIDENTIAL77.9840400
100%
RESIDENTIAL94.0921210
100%
RESIDENTIAL94.7216160
100%
RESIDENTIAL95.34330
100%
RESIDENTIAL106.47220
100%

Wing G

TypeCarpet (sq.ft)TotalBookedAvailableStatus
RESIDENTIAL62.3388844
95%

Wing H

TypeCarpet (sq.ft)TotalBookedAvailableStatus
RESIDENTIAL62.3388844
95%

Construction Progress

WING A

Basement (if any)100%

Wing A

Excavation100%

WING A

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing A

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate97%

WING A

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.97%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing A

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%

WING A

Plinth100%
Podiums (if any) 0%

Wing A

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

WING A

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Wing A

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING A

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing A

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

WING B

Basement (if any)100%

Wing B

Excavation100%

WING B

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing B

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate97%

WING B

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.97%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing B

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%

WING B

Plinth100%
Podiums (if any) 0%

Wing B

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

WING B

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Wing B

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING B

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing B

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

WING C

Basement (if any)100%

Wing C

Excavation100%

WING C

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing C

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate97%

WING C

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.97%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing C

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%

WING C

Plinth100%
Podiums (if any) 0%

Wing C

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

WING C

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Wing C

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING C

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing C

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

WING D

Basement (if any)100%

Wing D

Excavation100%

WING D

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing D

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate96%

WING D

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.96%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing D

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%

WING D

Plinth100%
Podiums (if any) 0%

Wing D

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

WING D

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Wing D

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING D

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing D

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

WING E

Basement (if any)100%

Wing E

Excavation100%

WING E

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.61%

Wing E

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate38%

WING E

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.38%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises56%

Wing E

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises56%

WING E

Plinth100%
Podiums (if any) 0%

Wing E

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

WING E

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%

Wing E

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.74%

WING E

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks74%

Wing E

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing61%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

WING F

Basement (if any)100%

Wing F

Excavation100%

WING F

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing F

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate91%

WING F

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.91%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing F

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%

WING F

Plinth100%
Podiums (if any) 0%

Wing F

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

WING F

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Wing F

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING F

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing F

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

WING G

Basement (if any)100%

Wing G

Excavation100%

WING G

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.73%

Wing G

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate33%

WING G

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.33%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises58%

Wing G

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises58%

WING G

Plinth100%
Podiums (if any) 0%

Wing G

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises3%

WING G

Sanitary Fittings within the flats / premises3%
Slabs of Super Structure100%

Wing G

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.74%

WING G

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks74%

Wing G

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing73%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

WING H

Basement (if any)100%

Wing H

Excavation100%

WING H

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.54%

Wing H

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate29%

WING H

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.29%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%

Wing H

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises40%

WING H

Plinth100%
Podiums (if any) 0%

Wing H

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

WING H

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%

Wing H

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.60%

WING H

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%

Wing H

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing54%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space62%
Community Buildings35%
Community Buildings Club House35%
Covered car parkings100%
Electrical Meter Room, Sub-Station, Receiving Station80%
Energy management77%
Fire Protection And Fire Safety Requirements63%
Landscaping & Tree Planting60%
Open Parking100%
Sewerage (Chamber, Lines, Septic Tank , STP)83%
Solid Waste Management And Disposal50%
Storm Water Drains63%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water80%
Water Conservation, Rain water Harvesting100%
Water Supply76%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.