📞 +91 98200 30685✉️
RERA: A51800043517

ZEE NAYAK

by PRAGATEE ZEE
Kept in AbeyanceP51800004058

Project Information

RERA Certificate No.
P51800004058
Registration No.
REA51800009440
Developer
PRAGATEE ZEE
Project Bank
UNION BANK OF INDIA
Proposed Possession
2020-12-31
Revised Possession
2021-12-30
Extended Possession
2022-12-30
Buildings
1
Project Area
664.71 sq.m
Total FSI
1901.00
Approved FSI
225.00
Litigations
⚠️ Yes
MahaRERA QR
ZEE NAYAK
MahaRERA — P51800004058
Scan to verify on MahaRERA portal

Wing-wise Details

🅿️Closed Parking27
📅Completion2021-12-21

Apartment Configurations

Zee Nayak

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK56.02770
100%
1ROMMKITCHEN29.82110
100%
1ROOMKITCHEN18.39660
100%
1ROOMKITCHEN21.73110
100%
1ROOMKITCHEN22.85770
100%
1ROOMKITCHEN23.13110
100%
1ROOMKITCHEN27.87761
86%
1ROOMKITCHEN28.14651
83%
1ROOMKITCHEN39.48550
100%
1ROOMKITCHEN44.12110
100%
1ROOMKITCHEN122.9110
100%
SHOP8.45110
100%
SHOP44.96110
100%
SHOP48.3110
100%
SHOP54.06110
100%
SHOP100.7110
100%

Construction Progress

Zee Nayak

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate75%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises80%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises78%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.65%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing80%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure90%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station50%
Energy management
Fire Protection And Fire Safety Requirements50%
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Solid Waste Management And Disposal85%
Storm Water Drains50%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply50%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.