📞 +91 98200 30685✉️
RERA: A51800043517

Gulraj Paradise

by M/S Reliable Construction Partnership
Certificate SignedP51800004371

Project Information

RERA Certificate No.
P51800004371
Registration No.
REA51800013827
Registration Date
2023-10-10
Developer
M/S Reliable Construction Partnership
Architect
Atharva Consultants
Project Bank
BANK OF BARODA
Proposed Possession
2021-06-30
Revised Possession
2021-06-30
Extended Possession
2024-09-30
Total Units
35
Units Sold
24 (69%)
Buildings
2
Project Area
5693.08 sq.m
Total FSI
22367.16
Approved FSI
22166.27
MahaRERA QR
Gulraj Paradise
MahaRERA — P51800004371
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors25
Sanctioned25
🚗Open Parking15
🅿️Closed Parking1
📅Completion2020-12-31
🏗️Proposed Floors17
Sanctioned17
🅿️Closed Parking17
📅Completion2020-12-31

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1Bhk25.0000
0%
1Bhk31.450000762939453000
0%
1Bhk31.690000534057617000
0%
1Bhk32.529998779296875000
0%
1Bhk33.20000076293945000
0%
1Bhk33.41999816894531000
0%

Gulraj Paradise Wing A B C D - Sale

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK31.4584795
94%
1 BHK31.69928210
89%
1 BHK32.5346424
91%
1 BHK33.246388
83%
1 BHK33.4292884
96%

Ratnamal Tower

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK25.017017
0%

Construction Progress

GULRAJ PARADISE WING A B C D - SALE

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises73%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises39%
Slabs of Super Structure87%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks87%
Stilt Floor 0%

RATNAMAL TOWER

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises44%
Plinth0%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises37%
Slabs of Super Structure75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.