Redevelopment Of Niwara Co-Op Hsg Society Ltd

by The Niwara Co-Operative Housing Society Ltd Society
Certificate SignedP51800006264

Project Information

RERA Certificate No.
P51800006264
Registration No.
REA51800010721
Registration Date
2021-09-10
Developer
The Niwara Co-Operative Housing Society Ltd Society
Architect
Kavaiya & Associates
Project Bank
BANK OF BARODA
Proposed Possession
2024-06-30
Revised Possession
2024-06-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
984.30 sq.m
Total FSI
2657.00
Approved FSI
1444.00
MahaRERA QR
Redevelopment Of Niwara Co-Op Hsg Society Ltd
MahaRERA — P51800006264
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors8
Sanctioned8
🅿️Closed Parking33
📅Completion2023-12-31

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 Bhk40.81999969482422000
0%
1Bhk41.130001068115234000
0%
2 Bhk67.0199966430664000
0%
2 Bhk67.91000366210938000
0%
2 Bhk69.66999816894531000
0%
2Bhk67.19999694824219000
0%
3 Bhk79.7300033569336000
0%
3 Bhk94.43000030517578000
0%
3Bhk79.19999694824219000
0%
3Bhk87.94000244140625000
0%

Niwara

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK40.82624
33%
1 BHK41.13615
17%
2 BHK67.02303
0%
2 BHK67.2303
0%
2 BHK67.91101
0%
2 BHK69.67110
100%
3 BHK79.2321
67%
3 BHK79.73303
0%
3 BHK87.94101
0%
3 BHK94.43110
100%

Construction Progress

Niwara

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises25%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises25%
Plinth0%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure50%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor70%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure50%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Internal Roads & Footpaths
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.