RERA: A51800043517

Allure Wings A To E

by Aadi Properties Llp Partnership
Certificate SignedP51800008521

Project Information

RERA Certificate No.
P51800008521
Registration No.
REA51800015920
Registration Date
2021-09-09
Developer
Aadi Properties Llp Partnership
Architect
Mandviwala Qutub
Project Bank
HDFC BANK
Proposed Possession
2021-12-30
Revised Possession
2021-12-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
5
Project Area
1489.48 sq.m
Total FSI
28170.74
Approved FSI
26670.74
MahaRERA QR
Allure Wings A To E
MahaRERA — P51800008521
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors22
Sanctioned22
📅Completion2020-12-31
🏗️Proposed Floors22
Sanctioned22
📅Completion2020-12-31
🏗️Proposed Floors22
Sanctioned22
📅Completion2020-12-31
🏗️Proposed Floors22
Sanctioned22
📅Completion2020-12-31
🏗️Proposed Floors22
Sanctioned22
📅Completion2020-12-31

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 Bhk42.56999969482422000
0%
1 Bhk42.83000183105469000
0%
1 Bhk43.310001373291016000
0%
1 Bhk46.7599983215332000
0%
1 Bhk46.77000045776367000
0%
1 Bhk47.099998474121094000
0%
1 Bhk47.400001525878906000
0%
2 Bhk58.2400016784668000
0%
2 Bhk61.790000915527344000
0%
2 Bhk66.94999694824219000
0%
2 Bhk67.81999969482422000
0%
2 Bhk68.05999755859375000
0%
2 Bhk68.08999633789062000
0%

Wing A Acacia

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK46.7721516
24%
2 BHK66.9542933
21%
2 BHK68.0621813
38%

Wing B Begonia

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK46.7621192
90%
1 BHK46.7721192
90%
2 BHK61.7921183
86%
2 BHK68.0921165
76%

Wing C Camellia

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK46.7620020
0%
1 BHK47.121120
5%
1 BHK47.4110
100%
2 BHK68.0942933
21%

Wing D Dahlia

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK42.5720173
85%
1 BHK42.8321192
90%
1 BHK43.31101
0%
2 BHK58.2421201
95%
2 BHK68.0921174
81%

Wing E Emillia

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK42.5721174
81%
2 BHK67.82422715
64%
2 BHK68.0621147
67%

Construction Progress

WING A ACACIA

Basement (if any)0%

Wing A Acacia

Excavation100%

WING A ACACIA

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing A Acacia

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

WING A ACACIA

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing A Acacia

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing70%

WING A ACACIA

Plinth0%
Podiums (if any) 0%

Wing A Acacia

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

WING A ACACIA

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Wing A Acacia

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING A ACACIA

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing A Acacia

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure100%

WING B BEGONIA

Basement (if any)0%

Wing B Begonia

Excavation100%

WING B BEGONIA

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing B Begonia

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

WING B BEGONIA

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing B Begonia

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing70%

WING B BEGONIA

Plinth0%
Podiums (if any) 0%

Wing B Begonia

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

WING B BEGONIA

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Wing B Begonia

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING B BEGONIA

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing B Begonia

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure100%

WING C CAMELLIA

Basement (if any)0%

Wing C Camellia

Excavation100%

WING C CAMELLIA

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing C Camellia

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

WING C CAMELLIA

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing C Camellia

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing70%

WING C CAMELLIA

Plinth0%
Podiums (if any) 0%

Wing C Camellia

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

WING C CAMELLIA

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Wing C Camellia

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING C CAMELLIA

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing C Camellia

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure100%

WING D DAHLIA

Basement (if any)0%

Wing D Dahlia

Excavation100%

WING D DAHLIA

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing D Dahlia

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

WING D DAHLIA

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing D Dahlia

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing70%

WING D DAHLIA

Plinth0%
Podiums (if any) 0%

Wing D Dahlia

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

WING D DAHLIA

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Wing D Dahlia

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING D DAHLIA

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing D Dahlia

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure100%

WING E EMILLIA

Basement (if any)0%

Wing E Emillia

Excavation100%

WING E EMILLIA

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing E Emillia

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

WING E EMILLIA

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing E Emillia

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing70%

WING E EMILLIA

Plinth0%
Podiums (if any) 0%

Wing E Emillia

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

WING E EMILLIA

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Wing E Emillia

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING E EMILLIA

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing E Emillia

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
BASEMENT100%
CHILDRENS PLAY AREA100%
CLUB HOUSE AND LEISURE AMENITIES90%
Community Buildings25%
Electrical Meter Room, Sub-Station, Receiving Station100%
Energy management100%
Fire Protection And Fire Safety Requirements100%
Landscaping & Tree Planting90%
Open Parking80%
PLINTH100%
PODIUM100%
Sewerage (Chamber, Lines, Septic Tank , STP)100%
Solid Waste Management And Disposal100%
STILT100%
Storm Water Drains100%
Street Lighting100%
Treatment And Disposal Of Sewage And Sullage Water100%
Water Conservation, Rain water Harvesting100%
Water Supply100%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.