📞 +91 98200 30685✉️
RERA: A51800043517

Makarani Pada Phase 1

by K D Builders Partnership
Certificate SignedP51800008606

Project Information

RERA Certificate No.
P51800008606
Registration No.
REA51800013317
Registration Date
2021-09-09
Developer
K D Builders Partnership
Architect
Sky Tech Consultants
Project Bank
ICICI BANK LIMITED
Proposed Possession
2024-03-30
Revised Possession
2024-03-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
3
Project Area
10233.93 sq.m
Total FSI
16913.02
Approved FSI
12449.94
MahaRERA QR
Makarani Pada Phase 1
MahaRERA — P51800008606
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors23
Sanctioned23
📅Completion2023-03-31
🏗️Proposed Floors12
Sanctioned12
📅Completion1900-01-01
🏗️Proposed Floors24
Sanctioned24
📅Completion1900-01-01

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 Bhk25.0000
0%
1 Bhk34.459999084472656000
0%
1 Bhk34.709999084472656000
0%
1Bhk25.0000
0%
Balwadi20.90999984741211000
0%
Comemercial17.399999618530273000
0%
Commercial1.8600000143051147000
0%
Commercial10.220000267028809000
0%
Commercial14.210000038146973000
0%
Commercial14.3100004196167000
0%
Commercial16.350000381469727000
0%
Commercial17.09000015258789000
0%
Commercial18.950000762939453000
0%
Commercial20.899999618530273000
0%
Commercial30.0000
0%
Commercial34.459999084472656000
0%
Rc25.0000
0%
Society20.0000
0%
Welfare Center20.90999984741211000
0%
Welfarecenter20.90999984741211000
0%

Kaydee Solitaire Composite Building Wing B

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK34.4667625
93%
1 BHK34.7120191
95%
Commercial30.0101
0%
Commercial34.46110
100%

Makarani Pada Sra Chs Rehab Building No 1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK25.01060106
0%
Balwadi20.91101
0%
Commercial1.86101
0%
Commercial10.22101
0%
Commercial14.31101
0%
Commercial17.09101
0%
Commercial18.95101
0%
Commercial20.9101
0%
RC25.0505
0%
Society20.0101
0%
Welfare Center20.91101
0%

Makarani Pada Sra Chs Rehab Wing A

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK25.01750175
0%
Balwadi20.91202
0%
Comemercial17.4101
0%
Commercial14.21101
0%
Commercial16.35101
0%
Commercial18.95101
0%
RC25.0101
0%
Society20.0202
0%
WelfareCenter20.91202
0%

Construction Progress

Kaydee Solitaire Composite Building Wing B

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing30%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

Makarani Pada SRA CHS Rehab Building NO 1

Basement (if any)0%

Makarani Pada Sra Chs Rehab Building No 1

Excavation0%

Makarani Pada SRA CHS Rehab Building NO 1

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Makarani Pada Sra Chs Rehab Building No 1

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

Makarani Pada SRA CHS Rehab Building NO 1

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Makarani Pada Sra Chs Rehab Building No 1

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%

Makarani Pada SRA CHS Rehab Building NO 1

Plinth0%
Podiums (if any) 0%

Makarani Pada Sra Chs Rehab Building No 1

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

Makarani Pada SRA CHS Rehab Building NO 1

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Makarani Pada Sra Chs Rehab Building No 1

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

Makarani Pada SRA CHS Rehab Building NO 1

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Makarani Pada Sra Chs Rehab Building No 1

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

Makarani Pada SRA CHS Rehab Wing A

Basement (if any)100%

Makarani Pada Sra Chs Rehab Wing A

Excavation100%

Makarani Pada SRA CHS Rehab Wing A

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Makarani Pada Sra Chs Rehab Wing A

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

Makarani Pada SRA CHS Rehab Wing A

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Makarani Pada Sra Chs Rehab Wing A

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing30%

Makarani Pada SRA CHS Rehab Wing A

Plinth100%
Podiums (if any) 0%

Makarani Pada Sra Chs Rehab Wing A

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

Makarani Pada SRA CHS Rehab Wing A

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%

Makarani Pada Sra Chs Rehab Wing A

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

Makarani Pada SRA CHS Rehab Wing A

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Makarani Pada Sra Chs Rehab Wing A

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.