Project Information
RERA Certificate No.
P51800012707
Registration No.
REA51800022726
Developer
Chinnaiah Gowda
Architect
Swapnil Dasharath Sawant
Project Bank
The Bharat Co Operative Bank Mumbai Ltd
Proposed Possession
2022-11-01
Revised Possession
2023-11-01
Extended Possession
1900-01-01
Buildings
1
Project Area
1549.12 sq.m
Total FSI
3709.53
Approved FSI
109.73
Srushti Vihar
MahaRERA — P51800012707
MahaRERA — P51800012707
Scan to verify on MahaRERA portal
Wing-wise Details
🚗Open
Parking10
🅿️Closed Parking20
📅Completion1900-01-01
Apartment Configurations
Tilak Shram Saphalya Chs Ltd
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| A Wing | 38.29 | 42 | 36 | 6 | 86% |
| Bwing | 53.51 | 15 | 11 | 4 | 73% |
| Bwing | 82.28 | 15 | 11 | 4 | 73% |
| Bwing | 82.31 | 15 | 11 | 4 | 73% |
Construction Progress
Tilak Shram Saphalya Chs Ltd
RERA Registered Amenities
⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical Meter Room, Sub-Station, Receiving Station76%
⬜Energy management
✅Fire Protection And Fire Safety
Requirements50%
⬜Landscaping & Tree Planting
✅Open Parking 100%
✅Sewerage (Chamber, Lines, Septic Tank , STP)
✅Solid Waste Management And Disposal76%
✅Storm Water Drains
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Conservation, Rain water Harvesting
✅Water Supply100%