Certificate SignedP51800012791

Project Information

RERA Certificate No.
P51800012791
Registration No.
REA51800019161
Registration Date
2017-09-07
Developer
Avi Housing Realtors Partnership
Proposed Possession
2019-12-31
Revised Possession
2019-12-31
Extended Possession
2024-10-31
Units Sold
0
Buildings
1
Project Area
1673.10 sq.m
Total FSI
4293.18
Approved FSI
4293.18
MahaRERA QR
Avis Residency
MahaRERA — P51800012791
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors18
Sanctioned18
🚗Open Parking2
🅿️Closed Parking78
📅Completion2019-12-31

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2Bhk72.45999908447266000
0%
2Bhk72.58999633789062000
0%
3Bhk86.44000244140625000
0%
3Bhk88.08000183105469000
0%
3Bhk92.41000366210938000
0%
Shop36.290000915527344000
0%
Shop111.4800033569336000
0%

Avis Residency

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK72.46651
83%
2 BHK72.59110
100%
3 BHK86.44880
100%
3 BHK88.08761
86%
3 BHK92.41651
83%
Shop36.29110
100%
Shop111.48110
100%

Construction Progress

Avis Residency

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises90%
Overall Percentage of Completion of the work done For the entire Building /Wing92%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises80%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure95%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing80%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure95%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station80%
Energy management
Fire Protection And Fire Safety Requirements50%
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)100%
Solid Waste Management And Disposal
Storm Water Drains50%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply100%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.