Bandra North Gulmohar Avenue

by Shivalik Ventures Private Limited Company
Certificate SignedP51800014036

Project Information

RERA Certificate No.
P51800014036
Registration No.
REA51800026031
Registration Date
2021-09-09
Developer
Shivalik Ventures Private Limited Company
Architect
Paarshad Associates
Project Bank
AXIS BANK
Proposed Possession
2023-08-27
Revised Possession
1900-01-01
Extended Possession
2026-12-31
Units Sold
0
Buildings
14
Project Area
6617.78 sq.m
Total FSI
30109.02
Approved FSI
30109.02
MahaRERA QR
Bandra North Gulmohar Avenue
MahaRERA — P51800014036
Scan to verify on MahaRERA portal

Wing-wise Details

📅Completion2022-08-27
🏗️Proposed Floors19
Sanctioned19
⬇️Basements3
🅿️Closed Parking9
📅Completion2023-08-26
🏗️Proposed Floors19
Sanctioned19
⬇️Basements3
🅿️Closed Parking12
📅Completion2023-08-26
🏗️Proposed Floors19
Sanctioned19
⬇️Basements3
🅿️Closed Parking9
📅Completion2023-08-26
🏗️Proposed Floors19
Sanctioned19
⬇️Basements3
🅿️Closed Parking12
📅Completion2023-08-26
🏗️Proposed Floors19
Sanctioned19
⬇️Basements3
🅿️Closed Parking9
📅Completion2023-08-26
🏗️Proposed Floors19
Sanctioned19
⬇️Basements3
🅿️Closed Parking12
📅Completion2023-08-26
🏗️Proposed Floors19
Sanctioned19
⬇️Basements3
🅿️Closed Parking39
📅Completion2023-08-26
🏗️Proposed Floors19
Sanctioned19
⬇️Basements3
🅿️Closed Parking48
📅Completion2023-08-26
🏗️Proposed Floors19
Sanctioned19
⬇️Basements3
🅿️Closed Parking12
📅Completion2023-08-26
🏗️Proposed Floors19
Sanctioned19
⬇️Basements3
🅿️Closed Parking9
📅Completion2023-08-26
🏗️Proposed Floors19
Sanctioned19
⬇️Basements3
🅿️Closed Parking12
📅Completion2023-08-26
🏗️Proposed Floors19
Sanctioned19
⬇️Basements3
🅿️Closed Parking9
📅Completion2023-08-26

Apartment Configurations

Deleted

TypeCarpet (sq.ft)TotalBookedAvailableStatus
00000
0%
000000
0%

Gulmohar Avenue Wing A

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK29.96593029
51%

Gulmohar Avenue Wing B

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK29.9659581
98%

Gulmohar Avenue Wing C

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK29.9658580
100%

Gulmohar Avenue Wing D

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK29.9658580
100%

Gulmohar Avenue Wing E

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK29.9659590
100%

Gulmohar Avenue Wing F

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK29.9659590
100%

Gulmohar Avenue Wing G

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK58.8115411
27%
2 BHK59.55441034
23%
SHOP5.04110
100%
SHOP6.48110
100%
SHOP10.0110
100%
SHOP16.79110
100%
SHOP18.83101
0%
SHOP19.13110
100%
SHOP19.56101
0%
SHOP19.78110
100%
SHOP19.94110
100%
SHOP20.48110
100%
SHOP20.99110
100%

Gulmohar Avenue Wing H

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK58.8114113
7%
2 BHK59.5545144
2%
SHOP7.67110
100%
SHOP14.25110
100%
SHOP16.18110
100%
SHOP17.54110
100%
SHOP19.28110
100%
SHOP19.6110
100%
SHOP19.8101
0%
SHOP20.37110
100%
SHOP21.01101
0%

Gulmohar Avenue Wing I

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK29.96591940
32%
SHOP14.5110
100%
SHOP18.28110
100%
SHOP19.47110
100%
SHOP20.33101
0%

Gulmohar Avenue Wing J

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK29.91581840
31%
SHOP9.58110
100%
SHOP19.52110
100%
SHOP20.05101
0%
SHOP20.3110
100%
SHOP20.4101
0%

Gulmohar Avenue Wing K

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK29.9659752
12%
SHOP7.95101
0%
SHOP18.18101
0%
SHOP19.14101
0%
SHOP19.42101
0%
SHOP20.17101
0%

Gulmohar Avenue Wing L

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK29.96581246
21%
SHOP8.09101
0%
SHOP19.5101
0%
SHOP20.35101
0%
SHOP20.41101
0%

Construction Progress

DELETED

Basement (if any)0%

Deleted

Excavation0%

DELETED

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Deleted

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

DELETED

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Deleted

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%

DELETED

Plinth0%
Podiums (if any) 0%

Deleted

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

DELETED

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Deleted

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

DELETED

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Deleted

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

GULMOHAR AVENUE WING A

Basement (if any)0%

Gulmohar Avenue Wing A

Excavation0%

GULMOHAR AVENUE WING A

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Gulmohar Avenue Wing A

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

GULMOHAR AVENUE WING A

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Gulmohar Avenue Wing A

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%

GULMOHAR AVENUE WING A

Plinth0%
Podiums (if any) 0%

Gulmohar Avenue Wing A

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

GULMOHAR AVENUE WING A

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Gulmohar Avenue Wing A

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

GULMOHAR AVENUE WING A

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Gulmohar Avenue Wing A

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

GULMOHAR AVENUE WING B

Basement (if any)100%

Gulmohar Avenue Wing B

Excavation100%

GULMOHAR AVENUE WING B

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Gulmohar Avenue Wing B

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

GULMOHAR AVENUE WING B

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Gulmohar Avenue Wing B

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises80%

GULMOHAR AVENUE WING B

Plinth100%
Podiums (if any) 0%

Gulmohar Avenue Wing B

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

GULMOHAR AVENUE WING B

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Gulmohar Avenue Wing B

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.75%

GULMOHAR AVENUE WING B

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Gulmohar Avenue Wing B

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

GULMOHAR AVENUE WING C

Basement (if any)100%

Gulmohar Avenue Wing C

Excavation100%

GULMOHAR AVENUE WING C

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Gulmohar Avenue Wing C

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

GULMOHAR AVENUE WING C

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Gulmohar Avenue Wing C

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%

GULMOHAR AVENUE WING C

Plinth100%
Podiums (if any) 0%

Gulmohar Avenue Wing C

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

GULMOHAR AVENUE WING C

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Gulmohar Avenue Wing C

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.75%

GULMOHAR AVENUE WING C

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Gulmohar Avenue Wing C

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

GULMOHAR AVENUE WING D

Basement (if any)100%

Gulmohar Avenue Wing D

Excavation100%

GULMOHAR AVENUE WING D

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Gulmohar Avenue Wing D

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

GULMOHAR AVENUE WING D

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Gulmohar Avenue Wing D

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

GULMOHAR AVENUE WING D

Plinth100%
Podiums (if any) 0%

Gulmohar Avenue Wing D

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

GULMOHAR AVENUE WING D

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Gulmohar Avenue Wing D

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

GULMOHAR AVENUE WING D

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Gulmohar Avenue Wing D

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

GULMOHAR AVENUE WING E

Basement (if any)100%

Gulmohar Avenue Wing E

Excavation100%

GULMOHAR AVENUE WING E

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Gulmohar Avenue Wing E

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate80%

GULMOHAR AVENUE WING E

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Gulmohar Avenue Wing E

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing88%

GULMOHAR AVENUE WING E

Plinth100%
Podiums (if any) 0%

Gulmohar Avenue Wing E

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

GULMOHAR AVENUE WING E

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Gulmohar Avenue Wing E

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

GULMOHAR AVENUE WING E

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Gulmohar Avenue Wing E

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

GULMOHAR AVENUE WING F

Basement (if any)100%

Gulmohar Avenue Wing F

Excavation100%

GULMOHAR AVENUE WING F

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Gulmohar Avenue Wing F

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

GULMOHAR AVENUE WING F

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Gulmohar Avenue Wing F

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

GULMOHAR AVENUE WING F

Plinth100%
Podiums (if any) 0%

Gulmohar Avenue Wing F

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

GULMOHAR AVENUE WING F

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Gulmohar Avenue Wing F

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

GULMOHAR AVENUE WING F

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Gulmohar Avenue Wing F

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

GULMOHAR AVENUE WING G

Basement (if any)100%

Gulmohar Avenue Wing G

Excavation100%

GULMOHAR AVENUE WING G

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Gulmohar Avenue Wing G

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

GULMOHAR AVENUE WING G

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Gulmohar Avenue Wing G

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing20%

GULMOHAR AVENUE WING G

Plinth100%
Podiums (if any) 0%

Gulmohar Avenue Wing G

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

GULMOHAR AVENUE WING G

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Gulmohar Avenue Wing G

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

GULMOHAR AVENUE WING G

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Gulmohar Avenue Wing G

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure0%

GULMOHAR AVENUE WING H

Basement (if any)100%

Gulmohar Avenue Wing H

Excavation100%

GULMOHAR AVENUE WING H

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Gulmohar Avenue Wing H

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

GULMOHAR AVENUE WING H

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Gulmohar Avenue Wing H

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing10%

GULMOHAR AVENUE WING H

Plinth100%
Podiums (if any) 0%

Gulmohar Avenue Wing H

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

GULMOHAR AVENUE WING H

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Gulmohar Avenue Wing H

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

GULMOHAR AVENUE WING H

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Gulmohar Avenue Wing H

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

GULMOHAR AVENUE WING I

Basement (if any)0%

Gulmohar Avenue Wing I

Excavation100%

GULMOHAR AVENUE WING I

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Gulmohar Avenue Wing I

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

GULMOHAR AVENUE WING I

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Gulmohar Avenue Wing I

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing10%

GULMOHAR AVENUE WING I

Plinth0%
Podiums (if any) 0%

Gulmohar Avenue Wing I

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

GULMOHAR AVENUE WING I

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Gulmohar Avenue Wing I

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

GULMOHAR AVENUE WING I

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Gulmohar Avenue Wing I

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

GULMOHAR AVENUE WING J

Basement (if any)0%

Gulmohar Avenue Wing J

Excavation0%

GULMOHAR AVENUE WING J

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Gulmohar Avenue Wing J

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

GULMOHAR AVENUE WING J

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Gulmohar Avenue Wing J

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%

GULMOHAR AVENUE WING J

Plinth0%
Podiums (if any) 0%

Gulmohar Avenue Wing J

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

GULMOHAR AVENUE WING J

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Gulmohar Avenue Wing J

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

GULMOHAR AVENUE WING J

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Gulmohar Avenue Wing J

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

GULMOHAR AVENUE WING K

Basement (if any)0%

Gulmohar Avenue Wing K

Excavation0%

GULMOHAR AVENUE WING K

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Gulmohar Avenue Wing K

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

GULMOHAR AVENUE WING K

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Gulmohar Avenue Wing K

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%

GULMOHAR AVENUE WING K

Plinth0%
Podiums (if any) 0%

Gulmohar Avenue Wing K

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

GULMOHAR AVENUE WING K

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Gulmohar Avenue Wing K

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

GULMOHAR AVENUE WING K

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Gulmohar Avenue Wing K

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

GULMOHAR AVENUE WING L

Basement (if any)0%

Gulmohar Avenue Wing L

Excavation0%

GULMOHAR AVENUE WING L

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Gulmohar Avenue Wing L

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

GULMOHAR AVENUE WING L

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Gulmohar Avenue Wing L

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%

GULMOHAR AVENUE WING L

Plinth0%
Podiums (if any) 0%

Gulmohar Avenue Wing L

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

GULMOHAR AVENUE WING L

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Gulmohar Avenue Wing L

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

GULMOHAR AVENUE WING L

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Gulmohar Avenue Wing L

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

RERA Registered Amenities

Aggregate area of recreational Open Space
CHILDERNS PLAY AREA
Community Buildings
DG SETS
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
SPACE FOR FITNESS CENTER
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.