RERA: A51800043517

Vishwakarma Nagar Chsl-Phase 2

by Ssakash Developers & Builders Partnership
Certificate SignedP51800014214

Project Information

RERA Certificate No.
P51800014214
Registration No.
REA51800026414
Registration Date
2017-11-16
Developer
Ssakash Developers & Builders Partnership
Architect
Space Vision
Project Bank
HDFC BANK
Proposed Possession
2019-12-31
Revised Possession
2019-12-31
Extended Possession
2022-12-30
Units Sold
0
Buildings
2
Project Area
2925.80 sq.m
Total FSI
9477.00
Approved FSI
7245.61
MahaRERA QR
Vishwakarma Nagar Chsl-Phase 2
MahaRERA — P51800014214
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors6
Sanctioned6
⬇️Basements1
🅿️Closed Parking1
📅Completion2021-12-31
🏗️Proposed Floors22
Sanctioned22
🅿️Closed Parking69
📅Completion2021-12-31

Apartment Configurations

D

TypeCarpet (sq.ft)TotalBookedAvailableStatus
BASEMENT17.0101
0%
MEDITATION CENTER198.0101
0%

Phase 2- A Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK53.4113130
100%
2 BHK55.74110
100%
2 BHK56.7622220
100%
2 BHK58.06110
100%
2 BHK60.1110
100%
2 BHK65.49110
100%
3 BHK74.78220
100%
3 BHK76.55110
100%
BLOCK31.67110
100%
COMMERCIAL378.0101
0%
DUPLEX334.45110
100%
OFFICE117.61110
100%
OFFICE129.69110
100%
SHOP36.51110
100%
SHOP36.69110
100%
SHOP38.64110
100%
Shop55.36110
100%

Construction Progress

D

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Plinth0%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

PHASE 2- A WING

Basement (if any)100%

Phase 2- A Wing

Excavation100%

PHASE 2- A WING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%

Phase 2- A Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate92%

PHASE 2- A WING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.92%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%

Phase 2- A Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises90%

PHASE 2- A WING

Plinth100%
Podiums (if any) 0%

Phase 2- A Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises90%

PHASE 2- A WING

Sanitary Fittings within the flats / premises90%
Slabs of Super Structure92%

Phase 2- A Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.92%

PHASE 2- A WING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks92%

Phase 2- A Wing

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing90%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure92%

RERA Registered Amenities

Aggregate area of recreational Open Space1%
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station90%
Energy management
Fire Protection And Fire Safety Requirements90%
Landscaping & Tree Planting100%
Open Parking50%
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Solid Waste Management And Disposal90%
Storm Water Drains90%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting90%
Water Supply90%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly