📞 +91 98200 30685✉️
RERA: A51800043517

Izarra

by Orno Infraprojects Pvt Ltd Company
Certificate SignedP51800018888

Project Information

RERA Certificate No.
P51800018888
Registration No.
REA51800047185
Registration Date
2024-04-24
Developer
Orno Infraprojects Pvt Ltd Company
Architect
Skyline Infrabuilt Consultantspvt Ltd
Project Bank
ICICI BANK LIMITED
Proposed Possession
2022-12-30
Revised Possession
1900-01-01
Extended Possession
2024-09-30
Units Sold
0
Buildings
1
Project Area
831.90 sq.m
Total FSI
3941.47
Approved FSI
2233.95
MahaRERA QR
Izarra
MahaRERA — P51800018888
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors18
Sanctioned18
⬇️Basements2
🅿️Closed Parking28
📅Completion2021-12-31

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3Bhk113.80999755859375000
0%

Izarra

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3 BHK113.8127216
78%

Construction Progress

IZARRA

Basement (if any)100%

Izarra

Excavation100%

IZARRA

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Izarra

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

IZARRA

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Izarra

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

IZARRA

Plinth100%
Podiums (if any) 100%

Izarra

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

IZARRA

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%

Izarra

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

IZARRA

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Izarra

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements100%
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)100%
Solid Waste Management And Disposal
Storm Water Drains100%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply100%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.