📞 +91 98200 30685✉️
RERA: A51800043517

Rite Oscar

by Rite Properties Partnership
Certificate SignedP51800020831

Project Information

RERA Certificate No.
P51800020831
Registration No.
REA51800055713
Registration Date
2020-06-25
Developer
Rite Properties Partnership
Architect
Ms Tanvi Dedhia
Project Bank
HDFC BANK
Proposed Possession
2021-06-30
Revised Possession
1900-01-01
Extended Possession
2022-12-30
Units Sold
0
Buildings
1
Project Area
472.00 sq.m
Total FSI
1223.64
MahaRERA QR
Rite Oscar
MahaRERA — P51800020831
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors11
Sanctioned11
🅿️Closed Parking7
📅Completion2020-12-31

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1Bhk35.400001525878906000
0%
1Bhk37.720001220703125000
0%
1Bhk39.02000045776367000
0%
2Bhk45.34000015258789000
0%
2Bhk49.2400016784668000
0%
Shop21.649999618530273000
0%

Rite Oscar

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK35.4330
100%
1 BHK37.72211
50%
1 BHK39.02110
100%
2 BHK45.34110
100%
2 BHK49.24550
100%
Shop21.65101
0%

Construction Progress

Rite Oscar

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station100%
Energy management
Fire Protection And Fire Safety Requirements100%
Landscaping & Tree Planting100%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)100%
Solid Waste Management And Disposal
Storm Water Drains100%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting100%
Water Supply100%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.