Manas Rangoli Residency

by Rangoli Developers Partnership
Certificate SignedP51800045413
šŸ’¬ WhatsAppšŸ“ž Call

Project Information

RERA Certificate No.
P51800045413
Registration No.
REA51800107960
Registration Date
2022-05-18
Developer
Rangoli Developers Partnership
Architect
Anj Engineering Consultants Llp
Project Bank
SARASWAT COOPERATIVE BANK LIMITED
Proposed Possession
2024-03-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
938.13 sq.m
Total FSI
2527.18
Approved FSI
1876.26
MahaRERA QR
Manas Rangoli Residency
MahaRERA — P51800045413
Scan to verify on MahaRERA portal

Wing-wise Details

šŸ—ļøProposed Floors8
āœ…Sanctioned8
šŸ“…Completion2024-03-31

Apartment Configurations

Manas Rangoli Residency

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3 BHK77.13330
100%
3 BHK77.14110
100%
3 BHK79.0651
83%
3 BHK80.59440
100%

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3Bhk77.12999725341797000
0%
3Bhk77.13999938964844000
0%
3Bhk79.0000
0%
3Bhk80.58999633789062000
0%

Construction Progress

MANAS RANGOLI RESIDENCY

Basement (if any)100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Manas Rangoli Residency

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

⬜Aggregate area of recreational Open Space
⬜Community Buildings
āœ…Electrical Meter Room, Sub-Station, Receiving Station100%
āœ…Energy management
āœ…Fire Protection And Fire Safety Requirements100%
āœ…Landscaping & Tree Planting100%
⬜Open Parking
āœ…Sewerage (Chamber, Lines, Septic Tank , STP)100%
⬜Solid Waste Management And Disposal
āœ…Storm Water Drains100%
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
āœ…Water Conservation, Rain water Harvesting100%
āœ…Water Supply100%
CallWhatsApp
āœ‰ļø

Get in Touch

Our team will connect with you shortly

+91
šŸ”’ Your details are secure with us
⚔ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.
šŸ‘‹ Looking for the right project? Let me help you find it!
šŸ—ļø
MPE Project Advisor
ā— Online now