RERA: A51800043517

Bc Corp Arista

by Tristar Development Llp Partnership
Certificate SignedP51800046486

Project Information

RERA Certificate No.
P51800046486
Registration No.
REA51800107539
Registration Date
2022-08-25
Developer
Tristar Development Llp Partnership
Architect
Ibadurrehman Momin
Project Bank
BHARAT COOPERATIVE BANK MUMBAI LIMITED
Proposed Possession
2025-12-31
Total Units
151
Units Sold
91 (60%)
Project Area
1682.35 sq.m
Total FSI
9089.25
Approved FSI
2349.41
MahaRERA QR
Bc Corp Arista
MahaRERA — P51800046486
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors24
Sanctioned24
🏠Habitable20
🅿️Closed Parking62
📅Completion2025-12-31
🏗️Proposed Floors22
Sanctioned22
🏠Habitable19
🅿️Closed Parking83
📅Completion2025-12-31

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1.5 Bhk37.060001373291016000
0%
2Bhk47.650001525878906000
0%
2Bhk47.79999923706055000
0%
2Bhk53.75000
0%
2Bhk57.79999923706055000
0%
2Bhk Rehab47.79999923706055000
0%
3Bhk69.51000213623047000
0%
3Bhk81.68000030517578000
0%

A-Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1.5 BHK37.061495
64%
2 BHK47.65220
100%
2 BHK47.8413
25%
2 BHK53.75101
0%
2 BHK REHAB47.854540
100%
3 BHK69.51101
0%

B-Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK57.8522923
56%
3 BHK81.6815123
80%

Construction Progress

A-WING

Basement (if any)100%

A-Wing

Excavation100%

A-WING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.72%

A-Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

A-WING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises84%

A-Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%

A-WING

Plinth100%
Podiums (if any) 100%

A-Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

A-WING

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure95%

A-Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

A-WING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%

A-Wing

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure18%

B-WING

Basement (if any)100%

B-Wing

Excavation100%

B-WING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.72%

B-Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

B-WING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises84%

B-Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%

B-WING

Plinth100%
Podiums (if any) 100%

B-Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

B-WING

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure95%

B-Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

B-WING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%

B-Wing

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure18%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.