RERA: A51800043517

Ridhi Sidhi

by Kesar Infra Llp Partnership
Certificate SignedP51800046974

Project Information

RERA Certificate No.
P51800046974
Registration No.
REA51800116055
Registration Date
2025-08-25
Developer
Kesar Infra Llp Partnership
Architect
Premal K Gogri
Project Bank
ICICI BANK LIMITED
Proposed Possession
2025-06-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
130
Units Sold
16 (12%)
Buildings
4
Project Area
3155.15 sq.m
Total FSI
8516.23
Approved FSI
7758.23
MahaRERA QR
Ridhi Sidhi
MahaRERA — P51800046974
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors13
Sanctioned13
🏠Habitable12
🔢Total Units24
🏡Residential24
🅿️Closed Parking1
📅Completion2025-06-30
🏗️Proposed Floors13
Sanctioned13
🏠Habitable12
🔢Total Units38
🏡Residential38
🅿️Closed Parking1
📅Completion2025-06-30
🏗️Proposed Floors13
Sanctioned13
🏠Habitable12
🔢Total Units39
🏡Residential39
🅿️Closed Parking1
📅Completion2025-06-30
🏗️Proposed Floors13
Sanctioned13
🏠Habitable12
🔢Total Units29
🏡Residential29
🅿️Closed Parking1
📅Completion2025-06-30

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1Bhk34.470001220703125000
0%
1Bhk36.70000076293945000
0%
1Bhk40.22999954223633000
0%
1Bhk44.779998779296875000
0%
2.5Bhk82.77999877929688000
0%
2Bhk52.68000030517578000
0%
2Bhk62.619998931884766000
0%
2Bhk68.55999755859375000
0%
2Bhk72.6500015258789000
0%
3Bhk87.69999694824219000
0%
3Bhk108.97000122070312000
0%

Wing A

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK52.68202
0%
2 BHK62.62220
100%

Wing B

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK34.47211
50%
1 BHK36.7101
0%
1 BHK40.23101
0%

Wing C

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK44.78110
100%
2 BHK62.62835
38%
2 BHK72.65615
17%
2.5 BHK82.78615
17%

Wing D

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK68.56716
14%
3 BHK87.71019
10%
3 BHK108.97321
67%

Construction Progress

WING A

Basement (if any)100%

Wing A

Excavation100%

WING A

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.40%

Wing A

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate20%

WING A

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%

Wing A

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises30%

WING A

Plinth100%
Podiums (if any) 100%

Wing A

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

WING A

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure80%

Wing A

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.80%

WING A

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%

Wing A

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing25%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure70%

WING B

Basement (if any)100%

Wing B

Excavation100%

WING B

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.25%

Wing B

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate20%

WING B

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30%

Wing B

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises30%

WING B

Plinth100%
Podiums (if any) 100%

Wing B

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

WING B

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure70%

Wing B

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.80%

WING B

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%

Wing B

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing25%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure70%

WING C

Basement (if any)100%

Wing C

Excavation100%

WING C

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%

Wing C

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50%

WING C

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%

Wing C

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises60%
Overall Percentage of Completion of the work done For the entire Building /Wing82%

WING C

Plinth100%
Podiums (if any) 100%

Wing C

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises50%

WING C

Sanitary Fittings within the flats / premises50%
Slabs of Super Structure100%

Wing C

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.80%

WING C

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%

Wing C

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing80%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

WING D

Basement (if any)100%

Wing D

Excavation100%

WING D

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%

Wing D

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate20%

WING D

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%

Wing D

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises60%
Overall Percentage of Completion of the work done For the entire Building /Wing77%

WING D

Plinth100%
Podiums (if any) 100%

Wing D

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises50%

WING D

Sanitary Fittings within the flats / premises50%
Slabs of Super Structure100%

Wing D

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.80%

WING D

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%

Wing D

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing60%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station50%
Energy management
Fire Protection And Fire Safety Requirements50%
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)75%
Solid Waste Management And Disposal
Storm Water Drains50%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting75%
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.