Shree Gangeshwar Chs Ltd
by Enrich Infrastructure
Project Information
RERA Certificate No.
P51800049955
Registration No.
REA51800128654
Registration Date
2023-03-06
Developer
Enrich Infrastructure
Architect
Mayuree Consultants
Project Bank
ICICI BANK LIMITED
Proposed Possession
2024-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
671.50 sq.m
Total FSI
3018.84
Approved FSI
3018.84
Shree Gangeshwar Chs Ltd
MahaRERA — P51800049955
MahaRERA — P51800049955
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors12
✅Sanctioned12
🅿️Closed Parking12
📅Completion2024-12-31
Apartment Configurations
None
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1Bhk | 27.5 | 0 | 0 | 0 | 0% |
| 1Bhk | 28.239999771118164 | 0 | 0 | 0 | 0% |
| 1Bhk | 29.540000915527344 | 0 | 0 | 0 | 0% |
| 1Bhk | 30.3799991607666 | 0 | 0 | 0 | 0% |
| 1Bhk | 34.099998474121094 | 0 | 0 | 0 | 0% |
| 1Bhk | 34.189998626708984 | 0 | 0 | 0 | 0% |
| 1Bhk | 34.279998779296875 | 0 | 0 | 0 | 0% |
| 1Rk | 23.229999542236328 | 0 | 0 | 0 | 0% |
| Rehab 1Bhk | 27.8700008392334 | 0 | 0 | 0 | 0% |
Shree Gangeshwar Chs Ltd
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 27.5 | 10 | 4 | 6 | 40% |
| 1 BHK | 28.24 | 10 | 9 | 1 | 90% |
| 1 BHK | 29.54 | 10 | 0 | 10 | 0% |
| 1 BHK | 30.38 | 10 | 9 | 1 | 90% |
| 1 BHK | 34.1 | 1 | 0 | 1 | 0% |
| 1 BHK | 34.19 | 1 | 0 | 1 | 0% |
| 1 BHK | 34.28 | 1 | 0 | 1 | 0% |
| 1RK | 23.23 | 10 | 3 | 7 | 30% |
| REHAB 1BHK | 27.87 | 40 | 0 | 40 | 0% |
Construction Progress
SHREE GANGESHWAR CHS LTD
Shree Gangeshwar Chs Ltd
SHREE GANGESHWAR CHS LTD
Shree Gangeshwar Chs Ltd
SHREE GANGESHWAR CHS LTD
Shree Gangeshwar Chs Ltd
SHREE GANGESHWAR CHS LTD
Shree Gangeshwar Chs Ltd
SHREE GANGESHWAR CHS LTD
Shree Gangeshwar Chs Ltd
SHREE GANGESHWAR CHS LTD
Shree Gangeshwar Chs Ltd
RERA Registered Amenities
⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical Meter Room, Sub-Station, Receiving Station
⬜Energy management
✅Fire Protection And Fire Safety
Requirements
✅Landscaping & Tree Planting
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)
✅Solid Waste Management And Disposal
✅Storm Water Drains
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Conservation, Rain water Harvesting
✅Water Supply