Tarabaug

by Darshan Developers Partnership
Certificate SignedP51900008495

Project Information

RERA Certificate No.
P51900008495
Registration No.
REA51900017949
Registration Date
2021-09-09
Developer
Darshan Developers Partnership
Project Bank
YES BANK
Proposed Possession
2026-12-30
Revised Possession
2026-12-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
8
Project Area
9171.47 sq.m
Total FSI
22928.00
Approved FSI
22504.00
MahaRERA QR
Tarabaug
MahaRERA — P51900008495
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors4
Sanctioned4
📅Completion2026-12-30
🏗️Proposed Floors4
Sanctioned4
📅Completion2026-12-30
🏗️Proposed Floors3
Sanctioned3
📅Completion2026-12-30
🏗️Proposed Floors9
Sanctioned9
🅿️Closed Parking1
📅Completion2026-12-30
🏗️Proposed Floors16
Sanctioned16
🅿️Closed Parking1
📅Completion2026-12-30
🏗️Proposed Floors8
Sanctioned8
🅿️Closed Parking1
📅Completion2026-12-30
🏗️Proposed Floors30
Sanctioned30
🅿️Closed Parking8
📅Completion2026-12-30
🏗️Proposed Floors24
Sanctioned24
🅿️Closed Parking5
📅Completion2026-12-30

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1Hk27.940000534057617000
0%
1Hk28.299999237060547000
0%
2Bhk49.0000
0%
2Bhk54.25000
0%
2Bhk56.06999969482422000
0%
2Bhk67.0000
0%
3Bhk67.9000015258789000
0%
Nr25.229999542236328000
0%
Nr27.690000534057617000
0%
Nr47.9900016784668000
0%
Nr53.91999816894531000
0%
Nr87.45999908447266000
0%
Nr119.8499984741211000
0%
Nr135.5800018310547000
0%
Nr237.0000
0%
R2bhk54.88999938964844000
0%
R2bhk256.84000015258789000
0%
R2bhk368.44000244140625000
0%
R2bhk468.66000366210938000
0%
R3bhk68.54000091552734000
0%
Room20.90999984741211000
0%

Building No 3

TypeCarpet (sq.ft)TotalBookedAvailableStatus
ROOM20.9120200
100%

Building No 6

TypeCarpet (sq.ft)TotalBookedAvailableStatus
NR25.23110
100%
NR27.69110
100%
NR47.99110
100%
NR53.92110
100%
NR119.85330
100%

Building No 7

TypeCarpet (sq.ft)TotalBookedAvailableStatus
NR87.46110
100%
NR135.58110
100%
NR237.0110
100%

Ganesh Darshan

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1HK27.9449490
100%
1HK28.3770
100%

Parking Structure

TypeCarpet (sq.ft)TotalBookedAvailableStatus
R2 BHK54.8928280
100%
R2 BHK256.8451510
100%
R2 BHK368.4422220
100%
R2 BHK468.6622220
100%
R3 BHK68.5428280
100%

Parshwa Darshan

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK49.0550
100%

Rushabh

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK54.2527270
100%
2 BHK56.0750482
96%
3 BHK67.926242
92%

Rushabh 2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK67.0110
100%

Construction Progress

BUILDING NO 3

Basement (if any)0%

Building No 3

Excavation0%

BUILDING NO 3

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Building No 3

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUILDING NO 3

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Building No 3

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%

BUILDING NO 3

Plinth0%
Podiums (if any) 0%

Building No 3

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUILDING NO 3

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Building No 3

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUILDING NO 3

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Building No 3

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUILDING NO 6

Basement (if any)1%

Building No 6

Excavation60%

BUILDING NO 6

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%

Building No 6

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate10%

BUILDING NO 6

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%

Building No 6

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises60%

BUILDING NO 6

Plinth1%
Podiums (if any) 0%

Building No 6

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises50%

BUILDING NO 6

Sanitary Fittings within the flats / premises50%
Slabs of Super Structure4%

Building No 6

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.90%

BUILDING NO 6

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%

Building No 6

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing60%
X number of Basement(s) and Plinth1%
X number of Podiums0%
X number of Slabs of Super Structure4%

BUILDING NO 7

Basement (if any)0%

Building No 7

Excavation0%

BUILDING NO 7

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Building No 7

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUILDING NO 7

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Building No 7

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%

BUILDING NO 7

Plinth0%
Podiums (if any) 0%

Building No 7

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUILDING NO 7

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Building No 7

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUILDING NO 7

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Building No 7

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

GANESH DARSHAN

Basement (if any)1%

Ganesh Darshan

Excavation100%

GANESH DARSHAN

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Ganesh Darshan

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

GANESH DARSHAN

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Ganesh Darshan

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing61%

GANESH DARSHAN

Plinth1%
Podiums (if any) 0%

Ganesh Darshan

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

GANESH DARSHAN

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure8%

Ganesh Darshan

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

GANESH DARSHAN

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Ganesh Darshan

Stilt Floor1%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth1%
X number of Podiums0%
X number of Slabs of Super Structure8%

Parking Structure

Basement (if any)1%
Excavation50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Plinth1%
Podiums (if any) 3%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure4%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
Stilt Floor1%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth1%
X number of Podiums3%
X number of Slabs of Super Structure4%

PARSHWA DARSHAN

Basement (if any)1%

Parshwa Darshan

Excavation100%

PARSHWA DARSHAN

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Parshwa Darshan

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

PARSHWA DARSHAN

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Parshwa Darshan

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%

PARSHWA DARSHAN

Plinth1%
Podiums (if any) 0%

Parshwa Darshan

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises90%

PARSHWA DARSHAN

Sanitary Fittings within the flats / premises90%
Slabs of Super Structure7%

Parshwa Darshan

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

PARSHWA DARSHAN

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Parshwa Darshan

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth1%
X number of Podiums0%
X number of Slabs of Super Structure7%

RUSHABH

Basement (if any)1%

Rushabh

Excavation100%

RUSHABH

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Rushabh

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

RUSHABH

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Rushabh

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%

RUSHABH

Plinth1%
Podiums (if any) 0%

Rushabh

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

RUSHABH

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure29%

Rushabh

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

RUSHABH

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Rushabh

Stilt Floor1%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth1%
X number of Podiums0%
X number of Slabs of Super Structure29%

RUSHABH 2

Basement (if any)1%

Rushabh 2

Excavation100%

RUSHABH 2

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%

Rushabh 2

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate15%

RUSHABH 2

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.15%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%

Rushabh 2

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises80%
Overall Percentage of Completion of the work done For the entire Building /Wing48%

RUSHABH 2

Plinth1%
Podiums (if any) 0%

Rushabh 2

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises70%

RUSHABH 2

Sanitary Fittings within the flats / premises70%
Slabs of Super Structure23%

Rushabh 2

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.95%

RUSHABH 2

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%

Rushabh 2

Stilt Floor1%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing95%
X number of Basement(s) and Plinth1%
X number of Podiums0%
X number of Slabs of Super Structure23%

RERA Registered Amenities

Aggregate area of recreational Open Space10%
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station80%
Energy management
Fire Protection And Fire Safety Requirements80%
Landscaping & Tree Planting90%
Open Parking100%
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Solid Waste Management And Disposal
Storm Water Drains90%
Street Lighting90%
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting70%
Water Supply80%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.