Project Information

RERA Certificate No.
P51900011418
Registration No.
REA51900009745
Registration Date
2021-09-09
Developer
Twenty Five South Realty Limited
Architect
Spaceage Consultant
Project Bank
HDFC BANK
Proposed Possession
2026-12-30
Revised Possession
2026-12-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
1102.00 sq.m
Total FSI
28931.00
Approved FSI
27975.00
MahaRERA QR
25 South Tower A 11Th To 47Th Floor
MahaRERA — P51900011418
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors41
Sanctioned41
🅿️Closed Parking300
📅Completion2025-12-31

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3 Bhk Jodi 1272.05999755859375000
0%
3 Bhk Jodi2271.1600036621094000
0%
3Bhk136.02999877929688000
0%
3Bhk141.99000549316406000
0%
3Bhk144.86000061035156000
0%
4 Bhk Luxury217.08999633789062000
0%
4 Bhk Luxury290.29998779296875000
0%
4 Bhk Premium184.0500030517578000
0%
4.5 Bhk299.0299987792969000
0%
4.5 Bhk Luxury290.29998779296875000
0%
4Bhk222.08999633789062000
0%
Duplex1453.3399963378906000
0%
Duplex2408.2799987792969000
0%
Pent House793.989990234375000
0%

25 South 11Th To 47Th Floors

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3 BHK136.0324231
96%
3 BHK141.99110
100%
3 BHK144.86110
100%
3 BHK Jodi 1272.06220
100%
3 BHK Jodi2271.16550
100%
4 BHK222.09220
100%
4 BHK Luxury217.0927270
100%
4 BHK Luxury290.31082
80%
4 BHK PREMIUM184.0534331
97%
4.5 BHK299.03110
100%
4.5 BHK Luxury290.3330
100%
DUPLEX1453.34110
100%
DUPLEX2408.28110
100%
Pent House793.99110
100%

Construction Progress

25 South 11th To 47th Floors

Basement (if any)100%

25 South 11Th To 47Th Floors

Excavation100%

25 South 11th To 47th Floors

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

25 South 11Th To 47Th Floors

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

25 South 11th To 47th Floors

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

25 South 11Th To 47Th Floors

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing100%

25 South 11th To 47th Floors

Plinth100%
Podiums (if any) 100%

25 South 11Th To 47Th Floors

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

25 South 11th To 47th Floors

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

25 South 11Th To 47Th Floors

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

25 South 11th To 47th Floors

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

25 South 11Th To 47Th Floors

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station100%
Energy management100%
Fire Protection And Fire Safety Requirements100%
Fitness Center
Landscaping & Tree Planting95%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)100%
Society Office
Solid Waste Management And Disposal100%
Storm Water Drains100%
Street Lighting99%
Swimming Pool
Treatment And Disposal Of Sewage And Sullage Water100%
Water Conservation, Rain water Harvesting100%
Water Supply100%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.