📞 +91 98200 30685✉️
RERA: A51800043517

SURYA GALAXY PHASE I

by SHUBH LAXMI REALTY Partnership
Certificate SignedP52000009302

Project Information

RERA Certificate No.
P52000009302
Registration No.
REA52000011867
Registration Date
2020-06-16
Developer
SHUBH LAXMI REALTY Partnership
Architect
Destinantion Architecture Interior Designs
Project Bank
INDIAN BANK
Proposed Possession
2021-01-31
Revised Possession
2021-01-31
Extended Possession
2022-07-31
Units Sold
0
Buildings
2
Project Area
5060.00 sq.m
Total FSI
2308.11
Approved FSI
2308.11
MahaRERA QR
SURYA GALAXY PHASE I
MahaRERA — P52000009302
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors9
Sanctioned9
🚗Open Parking6
🅿️Closed Parking1
📅Completion2020-07-31
🏗️Proposed Floors7
Sanctioned7
🚗Open Parking8
📅Completion1900-01-01

Apartment Configurations

A Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK28.242339
7%
1 BHK28.51707
0%
1 RK18.89707
0%
1 RK18.92707
0%
2 BHK32.1707
0%
2 BHK33.25707
0%
2 BHK33.81716
14%
SHOP16.5202
0%
SHOP16.8404
0%
SHOP19.89101
0%
SHOP21.03707
0%
SHOP21.42303
0%

B Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK30.40814014
0%
1 BHK30.77514014
0%
1 BHK31.54814014
0%
1 BHK32.39514014
0%
1RK21.43342042
0%

Construction Progress

A WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

B WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.