HIRAYS TULIP

by JAGANNATH DASHARATH HIRAY Individual
Certificate SignedP52000011105

Project Information

RERA Certificate No.
P52000011105
Registration No.
REA52000012854
Registration Date
2017-08-31
Developer
JAGANNATH DASHARATH HIRAY Individual
Architect
Mr Hemanr Dhavale
Project Bank
IDBI BANK
Proposed Possession
2017-12-31
Revised Possession
2017-12-31
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
299.80 sq.m
Total FSI
448.01
Approved FSI
448.01
MahaRERA QR
HIRAYS TULIP
MahaRERA — P52000011105
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors6
Sanctioned6
🚗Open Parking1
🅿️Closed Parking1
📅Completion1900-01-01

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1Bhk24.1299991607666000
0%
1Bhk24.389999389648438000
0%
1Bhk24.809999465942383000
0%
1Bhk26.920000076293945000
0%
1Rk17.75000
0%
1Rk18.020000457763672000
0%
1Rk18.600000381469727000
0%

Hirays Tulip

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK24.13110
100%
1 BHK24.39303
0%
1 BHK24.81330
100%
1 BHK26.92642
67%
1RK17.75220
100%
1RK18.02110
100%
1RK18.6110
100%

Construction Progress

HIRAYS TULIP

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station100%
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting100%
Open Parking100%
Sewerage (Chamber, Lines, Septic Tank , STP)100%
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply100%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.