RERA: A51800043517

Rainbow County - The Defence Enclave Phase - 1

by ANANTHAM EPIC HOMES LLP Partnership
Certificate SignedP52000027120

Project Information

RERA Certificate No.
P52000027120
Registration No.
REA52000079953
Registration Date
2021-09-08
Developer
ANANTHAM EPIC HOMES LLP Partnership
Project Bank
RBL Bank Limited
Proposed Possession
2025-06-30
Revised Possession
1900-01-01
Extended Possession
2026-06-30
Total Units
283
Units Sold
77 (27%)
Buildings
6
Project Area
13325.00 sq.m
Total FSI
25340.62
Approved FSI
24198.00
MahaRERA QR
Rainbow County - The Defence Enclave Phase - 1
MahaRERA — P52000027120
Scan to verify on MahaRERA portal

Wing-wise Details

🅿️Closed Parking7
📅Completion2025-06-30
🏗️Proposed Floors33
Sanctioned33
🏠Habitable26
🔢Total Units29
🏡Residential29
🅿️Closed Parking7
📅Completion2025-06-30
📅Completion2025-06-30
🏗️Proposed Floors33
Sanctioned33
🏠Habitable26
🔢Total Units33
🏡Residential33
🅿️Closed Parking5
📅Completion2025-06-30
🏗️Proposed Floors33
Sanctioned33
🏠Habitable26
🔢Total Units33
🏡Residential33
🅿️Closed Parking4
📅Completion2025-06-30
🅿️Closed Parking4
📅Completion2025-06-30
🏗️Proposed Floors33
Sanctioned33
🔢Total Units32
🏡Residential32
🏗️Proposed Floors33
Sanctioned33
🔢Total Units33
🏡Residential33
🏗️Proposed Floors33
Sanctioned33
🔢Total Units123
🏡Residential123

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2Bhk55.68000030517578000
0%
3Bhk74.4800033569336000
0%
3Bhk111.31999969482422000
0%
Na000
0%

Wing - A

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3 BHK98.7548741
15%

Wing - B

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3 BHK98.7548840
17%

Wing - C

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK49.8424222
8%
2 BHK50.6524420
17%
Shop8.94202
0%
Shop9.77202
0%
Shop9.98404
0%

Wing - D

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK49.841257
42%
2 BHK50.651257
42%
3 BHK68.6524420
17%

Wing - G

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK49.841275
58%
2 BHK50.651266
50%
3 BHK68.6524816
33%

Wing - H

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK49.8424717
29%
2 BHK50.6524222
8%

Construction Progress

Wing - AB

Basement (if any)28%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth28%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 0%

Wing - CH

Basement (if any)73%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth73%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 0%

Wing - DG

Basement (if any)42%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth42%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 0%

Wing - J

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 0%

Wing - K

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 0%

Wing - L

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 0%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Gymnasium
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Swimming Pool
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.