RERA: A51800043517

Plot No -77 Sector -17 Kalamboli Bus Depot

by CITY AND INDUSTRIAL DEVELOPMENT CORPORATION OF MAHARASHTRA LIMITED Company
Certificate SignedP52000028183

Project Information

RERA Certificate No.
P52000028183
Registration No.
REA52000084483
Registration Date
2021-09-08
Developer
CITY AND INDUSTRIAL DEVELOPMENT CORPORATION OF MAHARASHTRA LIMITED Company
Project Bank
STATE BANK OF INDIA
Proposed Possession
2025-06-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
9
Project Area
22570.59 sq.m
Total FSI
47962.51
Approved FSI
47782.13
MahaRERA QR
Plot No -77 Sector -17 Kalamboli Bus Depot
MahaRERA — P52000028183
Scan to verify on MahaRERA portal

Wing-wise Details

🅿️Closed Parking18
📅Completion2024-12-31
🏗️Proposed Floors27
Sanctioned27
🅿️Closed Parking43
📅Completion2024-12-31
🏗️Proposed Floors27
Sanctioned27
🅿️Closed Parking43
📅Completion2024-12-31
🏗️Proposed Floors27
Sanctioned27
🅿️Closed Parking43
📅Completion2024-12-31
🏗️Proposed Floors27
Sanctioned27
🅿️Closed Parking43
📅Completion2024-12-31
🏗️Proposed Floors27
Sanctioned27
🅿️Closed Parking43
📅Completion2024-12-31
🏗️Proposed Floors27
Sanctioned27
🅿️Closed Parking43
📅Completion2024-12-31
🏗️Proposed Floors27
Sanctioned27
🅿️Closed Parking43
📅Completion2024-12-31
🏗️Proposed Floors27
Sanctioned27
🅿️Closed Parking43
📅Completion2024-12-31
🏗️Proposed Floors1
Sanctioned1

Apartment Configurations

Commercial

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Shop22.11505
0%
Shop30.26101
0%
Shop30.3611011
0%
Shop51.36101
0%

E-B-01

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK27.110010
0%
1 BHK27.121600160
0%

E-B-02

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK27.110010
0%
1 BHK27.121600160
0%

E-B-03

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK27.110010
0%
1 BHK27.121600160
0%

E-B-04

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK27.110010
0%
1 BHK27.121600160
0%

E-B-05

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK27.110010
0%
1 BHK27.121600160
0%

E-B-06

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK27.110010
0%
1 BHK27.121600160
0%

E-B-07

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK27.110010
0%
1 BHK27.121600160
0%

E-B-08

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK27.110010
0%
1 BHK27.121600160
0%

Construction Progress

E-B-01

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure1%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 100%

E-B-02

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any) 15%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 0%

E-B-03

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure2%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 100%

E-B-04

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure14%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 100%

E-B-05

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises41%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises5%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 100%

E-B-06

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises44%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises4%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 100%

E-B-07

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises47%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises4%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 100%

E-B-08

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure4%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 100%

NA

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 0%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.