NINE STAR RESIDENCY ROHINI BUILDING
by TRINITY CONCRETE STRUCTURES PRIVATE LIMITED
Company
Project Information
RERA Certificate No.
P99000005167
Registration No.
REA99000016148
Registration Date
2017-08-10
Developer
TRINITY CONCRETE STRUCTURES PRIVATE LIMITED Company
Architect
Atulkumar Prajapati
Project Bank
IDBI BANK
Proposed Possession
2018-07-31
Revised Possession
2018-07-31
Extended Possession
2022-07-31
Units Sold
0
Buildings
1
Project Area
411.00 sq.m
Total FSI
704.00
Approved FSI
704.00
NINE STAR RESIDENCY ROHINI BUILDING
MahaRERA — P99000005167
MahaRERA — P99000005167
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors5
✅Sanctioned5
📅Completion1900-01-01
Apartment Configurations
None
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 Bhk | 28.6200008392334 | 0 | 0 | 0 | 0% |
| 1 Bhk | 28.700000762939453 | 0 | 0 | 0 | 0% |
| 1 Bhk | 29.479999542236328 | 0 | 0 | 0 | 0% |
| 2 Bhk | 37.13999938964844 | 0 | 0 | 0 | 0% |
Rohini Building
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 28.62 | 2 | 2 | 0 | 100% |
| 1 BHK | 28.7 | 8 | 0 | 8 | 0% |
| 1 BHK | 29.48 | 4 | 1 | 3 | 25% |
| 2 BHK | 37.14 | 4 | 1 | 3 | 25% |
Construction Progress
ROHINI BUILDING
Rohini Building
ROHINI BUILDING
Rohini Building
ROHINI BUILDING
Rohini Building
ROHINI BUILDING
Rohini Building
ROHINI BUILDING
Rohini Building
ROHINI BUILDING
Rohini Building
RERA Registered Amenities
⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical Meter Room, Sub-Station, Receiving Station
⬜Energy management
⬜Fire Protection And Fire Safety
Requirements
✅Landscaping & Tree Planting50%
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)20%
⬜Solid Waste Management And Disposal
✅Storm Water Drains
✅Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Conservation, Rain water Harvesting
✅Water Supply70%