Project Information

RERA Certificate No.
P99000009626
Registration No.
REA99000016618
Registration Date
2017-08-22
Developer
sky star enterprises Partnership
Architect
En Con
Project Bank
BANK OF MAHARASHTRA
Proposed Possession
2018-12-31
Revised Possession
2018-12-31
Extended Possession
2019-12-31
Units Sold
0
Buildings
1
Project Area
4839.12 sq.m
Total FSI
4968.12
Approved FSI
4726.16
MahaRERA QR
SKY TOWER
MahaRERA — P99000009626
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors16
Sanctioned16
🚗Open Parking50
🅿️Closed Parking8
📅Completion1900-01-01

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Residential3432.60009765625000
0%

Sky Tower

TypeCarpet (sq.ft)TotalBookedAvailableStatus
residential3432.61179423
80%

Construction Progress

sky tower

Basement (if any)100%

Sky Tower

Excavation100%

sky tower

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Sky Tower

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

sky tower

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5%

Sky Tower

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises5%
Overall Percentage of Completion of the work done For the entire Building /Wing33%

sky tower

Plinth100%
Podiums (if any) 0%

Sky Tower

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

sky tower

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure25%

Sky Tower

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.20%

sky tower

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks20%

Sky Tower

Stilt Floor80%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure25%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.