Project Information

RERA Certificate No.
P99000025272
Registration No.
REA99000071298
Registration Date
2021-09-08
Developer
AASHIRWAD DEVELOPERS Partnership
Architect
Umesh Kekre
Project Bank
HDFC BANK
Proposed Possession
2025-12-17
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
3
Project Area
2200.00 sq.m
Total FSI
2904.65
Approved FSI
1603.41
MahaRERA QR
Padmi Hari Complex
MahaRERA — P99000025272
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors8
Sanctioned8
🚗Open Parking7
📅Completion2024-12-17
🏗️Proposed Floors7
Sanctioned7
🚗Open Parking6
📅Completion2024-12-17
🏗️Proposed Floors7
Sanctioned7
🚗Open Parking6
📅Completion2024-12-17

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1Bhk28.75000
0%
1Bhk28.799999237060547000
0%
1Bhk29.450000762939453000
0%
1Bhk29.950000762939453000
0%
1Bhk30.0000
0%
1Bhk34.45000076293945000
0%
1Bhk34.599998474121094000
0%
1Bhk34.95000076293945000
0%
1Bhk35.04999923706055000
0%
1Bhk36.0000
0%
1Bhk38.79999923706055000
0%
1Rk20.600000381469727000
0%
2Bhk39.650001525878906000
0%
2Bhk39.75000
0%
2Bhk39.849998474121094000
0%
2Bhk49.900001525878906000
0%

A Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK35.05716
14%
1 BHK38.8808
0%
1RK20.6725
29%
2 BHK39.65725
29%
2 BHK39.75725
29%
2 BHK39.85725
29%

B Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK28.813211
15%
1 BHK29.95606
0%
1 BHK30.0707
0%
1 BHK34.6606
0%
1 BHK36.0707
0%

C Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK28.75716
14%
1 BHK28.8716
14%
1 BHK29.45707
0%
1 BHK34.45624
33%
1 BHK34.95707
0%
2 BHK49.9716
14%

Construction Progress

A wing

Basement (if any)0%

A Wing

Excavation100%

A wing

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

A Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

A wing

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%

A Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises10%
Overall Percentage of Completion of the work done For the entire Building /Wing31%

A wing

Plinth0%
Podiums (if any) 0%

A Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

A wing

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%

A Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

A wing

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%

A Wing

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure100%

B Wing

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises10%
Overall Percentage of Completion of the work done For the entire Building /Wing31%
Plinth0%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure100%

C Wing

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises10%
Overall Percentage of Completion of the work done For the entire Building /Wing31%
Plinth0%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.