šŸ“ž +91 98200 30685āœ‰ļø
RERA: A51800043517

Aaradhya Nine

by Micl Realty Llp Others
Certificate SignedP51800000229
šŸ’¬ WhatsAppšŸ“ž Call

Project Information

RERA Certificate No.
P51800000229
Registration No.
REA51800002935
Registration Date
2020-06-11
Developer
Micl Realty Llp Others
Architect
Architecture Plus
Project Bank
KOTAK MAHINDRA BANK LIMITED
Proposed Possession
2021-03-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
4
Project Area
2461.71 sq.m
Total FSI
16001.00
Approved FSI
15796.06
MahaRERA QR
Aaradhya Nine
MahaRERA — P51800000229
Scan to verify on MahaRERA portal

Wing-wise Details

šŸ—ļøProposed Floors18
āœ…Sanctioned18
ā¬‡ļøBasements1
šŸ…æļøClosed Parking39
šŸ“…Completion2020-09-30
šŸ—ļøProposed Floors18
āœ…Sanctioned18
ā¬‡ļøBasements1
šŸ…æļøClosed Parking57
šŸ“…Completion2020-09-30
šŸ—ļøProposed Floors18
āœ…Sanctioned18
ā¬‡ļøBasements1
šŸ…æļøClosed Parking29
šŸ“…Completion2020-09-30
šŸ—ļøProposed Floors18
āœ…Sanctioned18
ā¬‡ļøBasements1
šŸ…æļøClosed Parking29
šŸ“…Completion2020-09-30

Apartment Configurations

Wing A

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3 BHK79.2530264
87%
3 BHK90.9529281
97%

Wing B

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK56.1130300
100%
2 BHK66.6129290
100%

Wing C

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK\REHAB41.2515150
100%
1 BHK\REHAB41.4344440
100%

Wing D

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK41.43440
100%
1 BHK41.53440
100%
1 BHK\REHAB41.2515150
100%
1 BHK\REHAB41.4311110
100%
1 BHK\REHAB41.5311110
100%
1RK30.8415150
100%
2 BHK50.5414140
100%

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1Bhk41.43000030517578000
0%
1Bhk41.529998779296875000
0%
1Bhk\Rehab41.25000
0%
1Bhk\Rehab41.43000030517578000
0%
1Bhk\Rehab41.529998779296875000
0%
1Rk30.84000015258789000
0%
2Bhk50.540000915527344000
0%
2Bhk56.11000061035156000
0%
2Bhk66.61000061035156000
0%
3Bhk79.25000
0%
3Bhk90.94999694824219000
0%

Construction Progress

WING A

Basement (if any)100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

WING B

Basement (if any)100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

WING C

Basement (if any)100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

WING D

Basement (if any)100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing A

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

Wing B

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

Wing C

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

Wing D

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

⬜Aggregate area of recreational Open Space
⬜Community Buildings
āœ…Electrical Meter Room, Sub-Station, Receiving Station100%
⬜Energy management
āœ…FITNESS CENTER AT TERRACE OF WING A AND B100%
āœ…Fire Protection And Fire Safety Requirements100%
āœ…Landscaping & Tree Planting100%
⬜Open Parking
āœ…RECREATION AREA AT TERRACE OF WING A AND B100%
āœ…Sewerage (Chamber, Lines, Septic Tank , STP)100%
āœ…Solid Waste Management And Disposal100%
āœ…Storm Water Drains100%
⬜Street Lighting
āœ…Treatment And Disposal Of Sewage And Sullage Water100%
āœ…Water Conservation, Rain water Harvesting100%
āœ…Water Supply100%
CallWhatsApp
āœ‰ļø

Get in Touch

Our team will connect with you shortly

+91
šŸ”’ Your details are secure with us
⚔ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.
šŸ‘‹ Looking for the right project? Let me help you find it!
šŸ—ļø
MPE Project Advisor
ā— Online now