📞 +91 98200 30685✉️
RERA: A51800043517

Ghatkopar Avenue Aaradhya One Earth Phase I

by Man Realtors And Holdings Private Limited Company
Certificate SignedP51800024676

Project Information

RERA Certificate No.
P51800024676
Registration No.
REA51800070047
Registration Date
2021-09-08
Developer
Man Realtors And Holdings Private Limited Company
Project Bank
ICICI BANK LIMITED
Proposed Possession
2025-03-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
8
Project Area
3365.00 sq.m
Total FSI
40000.00
Approved FSI
40000.00
MahaRERA QR
Ghatkopar Avenue Aaradhya One Earth Phase I
MahaRERA — P51800024676
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors22
Sanctioned22
⬇️Basements3
🅿️Closed Parking28
📅Completion2024-03-31
🏗️Proposed Floors22
Sanctioned22
⬇️Basements3
🅿️Closed Parking29
📅Completion2024-03-31
🏗️Proposed Floors22
Sanctioned22
⬇️Basements3
🅿️Closed Parking17
📅Completion2024-03-31
🏗️Proposed Floors22
Sanctioned22
⬇️Basements3
🅿️Closed Parking25
📅Completion2024-03-31
🏗️Proposed Floors22
Sanctioned22
⬇️Basements3
🅿️Closed Parking13
📅Completion2024-03-31
🏗️Proposed Floors21
Sanctioned21
⬇️Basements3
🅿️Closed Parking90
📅Completion2024-03-31
🏗️Proposed Floors21
Sanctioned21
⬇️Basements3
🅿️Closed Parking47
📅Completion2024-03-31
🏗️Proposed Floors21
Sanctioned21
⬇️Basements3
🅿️Closed Parking45
📅Completion2024-03-31

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1.5 Bhk47.470001220703125000
0%
1Bhk45.34000015258789000
0%
2 Bhk With Balcony66.1500015258789000
0%
2 Bhk With Balcony75.06999969482422000
0%
2Bhk61.779998779296875000
0%
2Bhk66.43000030517578000
0%
2Bhkwithbalcony66.43000030517578000
0%
2Bhkwithbalcony67.08000183105469000
0%
3 Bhk With Balcony92.9000015258789000
0%
3Bhk92.9000015258789000
0%
3Bhk101.91000366210938000
0%
Shop23.0000
0%
Shop25.0000
0%
Shop40.0000
0%

Rehab Tower 1 - Alpha

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1.5 BHK47.471151150
100%

Rehab Tower 2 - Breeze

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1.5 BHK47.471161160
100%

Rehab Tower 3 - Coral

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1.5 BHK47.4766660
100%

Rehab Tower 4 - Delta

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1.5 BHK47.471001000
100%

Rehab Tower 5 - Eve

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1.5 BHK47.4751510
100%

Tower A - Avion

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK66.4344440
100%
2 BHKwithbalcony66.43110
100%
2 BHKwithbalcony67.0830300
100%
3 BHK92.913130
100%
3 BHK101.91110
100%
Shop23.0110
100%
Shop25.0110
100%
Shop40.0110
100%

Tower C - Casa

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK66.4331310
100%
2 BHK WITH BALCONY75.07110
100%
3 BHK WITH BALCONY92.915150
100%

Tower D - Dew

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK45.34110
100%
2 BHK61.7814140
100%
2 BHK WITH BALCONY66.1530300
100%

Construction Progress

REHAB TOWER 1 - ALPHA

Basement (if any)100%

Rehab Tower 1 - Alpha

Excavation100%

REHAB TOWER 1 - ALPHA

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Rehab Tower 1 - Alpha

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

REHAB TOWER 1 - ALPHA

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Rehab Tower 1 - Alpha

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

REHAB TOWER 1 - ALPHA

Plinth100%
Podiums (if any) 0%

Rehab Tower 1 - Alpha

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

REHAB TOWER 1 - ALPHA

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Rehab Tower 1 - Alpha

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

REHAB TOWER 1 - ALPHA

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Rehab Tower 1 - Alpha

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

REHAB TOWER 2 - BREEZE

Basement (if any)100%

Rehab Tower 2 - Breeze

Excavation100%

REHAB TOWER 2 - BREEZE

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Rehab Tower 2 - Breeze

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

REHAB TOWER 2 - BREEZE

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Rehab Tower 2 - Breeze

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

REHAB TOWER 2 - BREEZE

Plinth100%
Podiums (if any) 0%

Rehab Tower 2 - Breeze

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

REHAB TOWER 2 - BREEZE

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Rehab Tower 2 - Breeze

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

REHAB TOWER 2 - BREEZE

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Rehab Tower 2 - Breeze

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

REHAB TOWER 3 - CORAL

Basement (if any)100%

Rehab Tower 3 - Coral

Excavation100%

REHAB TOWER 3 - CORAL

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Rehab Tower 3 - Coral

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

REHAB TOWER 3 - CORAL

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Rehab Tower 3 - Coral

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

REHAB TOWER 3 - CORAL

Plinth100%
Podiums (if any) 0%

Rehab Tower 3 - Coral

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

REHAB TOWER 3 - CORAL

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Rehab Tower 3 - Coral

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

REHAB TOWER 3 - CORAL

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Rehab Tower 3 - Coral

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

REHAB TOWER 4 - DELTA

Basement (if any)100%

Rehab Tower 4 - Delta

Excavation100%

REHAB TOWER 4 - DELTA

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Rehab Tower 4 - Delta

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

REHAB TOWER 4 - DELTA

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Rehab Tower 4 - Delta

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

REHAB TOWER 4 - DELTA

Plinth100%
Podiums (if any) 0%

Rehab Tower 4 - Delta

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

REHAB TOWER 4 - DELTA

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Rehab Tower 4 - Delta

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

REHAB TOWER 4 - DELTA

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Rehab Tower 4 - Delta

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

REHAB TOWER 5 - EVE

Basement (if any)100%

Rehab Tower 5 - Eve

Excavation100%

REHAB TOWER 5 - EVE

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Rehab Tower 5 - Eve

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

REHAB TOWER 5 - EVE

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Rehab Tower 5 - Eve

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

REHAB TOWER 5 - EVE

Plinth100%
Podiums (if any) 0%

Rehab Tower 5 - Eve

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

REHAB TOWER 5 - EVE

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Rehab Tower 5 - Eve

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

REHAB TOWER 5 - EVE

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Rehab Tower 5 - Eve

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

TOWER A - AVION

Basement (if any)100%

Tower A - Avion

Excavation100%

TOWER A - AVION

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Tower A - Avion

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

TOWER A - AVION

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Tower A - Avion

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

TOWER A - AVION

Plinth100%
Podiums (if any) 0%

Tower A - Avion

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

TOWER A - AVION

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Tower A - Avion

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

TOWER A - AVION

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Tower A - Avion

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

TOWER C - CASA

Basement (if any)100%

Tower C - Casa

Excavation100%

TOWER C - CASA

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Tower C - Casa

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

TOWER C - CASA

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Tower C - Casa

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

TOWER C - CASA

Plinth100%
Podiums (if any) 0%

Tower C - Casa

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

TOWER C - CASA

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Tower C - Casa

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

TOWER C - CASA

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Tower C - Casa

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

TOWER D - DEW

Basement (if any)100%

Tower D - Dew

Excavation100%

TOWER D - DEW

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Tower D - Dew

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

TOWER D - DEW

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Tower D - Dew

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing80%

TOWER D - DEW

Plinth100%
Podiums (if any) 0%

Tower D - Dew

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

TOWER D - DEW

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%

Tower D - Dew

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

TOWER D - DEW

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Tower D - Dew

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station80%
Energy management
Fire Protection And Fire Safety Requirements80%
Landscaping & Tree Planting70%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)100%
Solid Waste Management And Disposal80%
Storm Water Drains100%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water80%
Water Conservation, Rain water Harvesting80%
Water Supply100%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.