Amisha Empire - Phase I

by Amisha Associates Partnership
Certificate Signed P51700010847
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700010847
Registration No.
REA51700021564
Registration Date
2017-08-31
Developer
Amisha Associates Partnership
Architect
Anish & Associates
Project Bank
BASSEIN CATHOLIC COOPERATIVE BANK LIMITED
Proposed Possession
2019-12-31
Revised Possession
2019-12-31
Extended Possession
2022-06-30
Units Sold
0
Buildings
3
Project Area
8710.00 sq.m
Total FSI
10966.61
Approved FSI
8262.61
MahaRERA QR
Amisha Empire - Phase I
MahaRERA — P51700010847
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors13
Sanctioned13
🅿️Closed Parking5
📅Completion2019-12-31
🏗️Proposed Floors16
Sanctioned16
🅿️Closed Parking6
📅Completion2019-12-31
🏗️Proposed Floors13
Sanctioned13
🅿️Closed Parking5
📅Completion2019-12-31

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1Bhk 35.16999816894531 0 0 0
0%
2Bhk 54.40999984741211 0 0 0
0%
3Bhk 73.30000305175781 0 0 0
0%
Office 2 73.16999816894531 0 0 0
0%
Office Space 224.3699951171875 0 0 0
0%
Office Space 418.739990234375 0 0 0
0%
Office Space 545.489990234375 0 0 0
0%
Shop 54.75 0 0 0
0%
Shop 68.81999969482422 0 0 0
0%
Shop 120.08999633789062 0 0 0
0%
Shop 129.58999633789062 0 0 0
0%
Shop 199.4499969482422 0 0 0
0%
Shop 331.70001220703125 0 0 0
0%
Shop 394.30999755859375 0 0 0
0%

Wing A

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 35.17 11 4 7
36%
2 BHK 54.41 20 9 11
45%
3 BHK 73.3 10 8 2
80%
Office 2 73.17 1 0 1
0%
Office space 418.74 1 0 1
0%
Shop 54.75 1 0 1
0%
Shop 68.82 1 0 1
0%
Shop 129.59 1 0 1
0%
Shop 331.7 1 0 1
0%

Wing B

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 54.41 52 30 22
58%
Office space 224.37 1 0 1
0%
Shop 120.09 1 0 1
0%
Shop 199.45 1 0 1
0%

Wing C

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 35.17 11 3 8
27%
2 BHK 54.41 20 11 9
55%
3 BHK 73.3 10 5 5
50%
Office space 545.49 1 0 1
0%
Shop 394.31 1 0 1
0%

Construction Progress

Wing A

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

Wing B

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

Wing C

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 100%
Energy management
Fire Protection And Fire Safety Requirements 100%
Landscaping & Tree Planting 100%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 100%
Solid Waste Management And Disposal
Storm Water Drains 100%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.