ANANT TARA
by ANANT CHHAYA DEVELOPERS
Partnership
Project Information
RERA Certificate No.
P51800027209
Registration No.
REA51800071206
Registration Date
2021-09-08
Developer
ANANT CHHAYA DEVELOPERS Partnership
Architect
Tanisha Creative Design Pvt Ltd
Project Bank
HDFC BANK
Proposed Possession
2025-06-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
2450.40 sq.m
Total FSI
7059.84
Approved FSI
5134.84
ANANT TARA
MahaRERA — P51800027209
MahaRERA — P51800027209
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors25
✅Sanctioned25
⬇️Basements1
📅Completion2024-12-31
Apartment Configurations
None
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1Bhk | 27.8799991607666 | 0 | 0 | 0 | 0% |
| 1Bhk | 38.61000061035156 | 0 | 0 | 0 | 0% |
| 1Bhk | 38.939998626708984 | 0 | 0 | 0 | 0% |
| 1Bhk | 40.849998474121094 | 0 | 0 | 0 | 0% |
| 2Bhk | 62.0099983215332 | 0 | 0 | 0 | 0% |
| Shop | 20.899999618530273 | 0 | 0 | 0 | 0% |
Anant Tara
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 27.88 | 136 | 0 | 136 | 0% |
| 1 BHK | 38.61 | 20 | 15 | 5 | 75% |
| 1 BHK | 38.94 | 20 | 15 | 5 | 75% |
| 1 BHK | 40.85 | 21 | 16 | 5 | 76% |
| 2 BHK | 62.01 | 64 | 40 | 24 | 62% |
| Shop | 20.9 | 1 | 0 | 1 | 0% |
Construction Progress
ANANT TARA
RERA Registered Amenities
✅
Aggregate area of recreational Open Space
⬜
Community Buildings
✅
Electrical Meter Room, Sub-Station, Receiving Station
90%
✅
Energy management
✅
Fire Protection And Fire Safety
Requirements
95%
✅
Landscaping & Tree Planting
⬜
Open Parking
✅
Sewerage (Chamber, Lines, Septic Tank , STP)
85%
⬜
Solid Waste Management And Disposal
✅
Storm Water Drains
80%
✅
Street Lighting
✅
Treatment And Disposal Of Sewage And Sullage Water
100%
✅
Water Conservation, Rain water Harvesting
80%
✅
Water Supply
85%