ARIHANT ANAIKA PHASE I

by ARIHANT VATIKA REALTY PRIVATE LIMITED Company
Certificate SignedP52000001869

Project Information

RERA Certificate No.
P52000001869
Registration No.
REA52000006832
Registration Date
2017-07-29
Developer
ARIHANT VATIKA REALTY PRIVATE LIMITED Company
Architect
Kiran K Awhale
Project Bank
ICICI BANK LIMITED
Proposed Possession
2018-12-30
Revised Possession
2018-12-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
12
Project Area
11726.39 sq.m
Total FSI
10165.90
Approved FSI
10165.90
MahaRERA QR
ARIHANT ANAIKA PHASE I
MahaRERA — P52000001869
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors5
Sanctioned5
🅿️Closed Parking1
📅Completion2018-12-30
🏗️Proposed Floors5
Sanctioned5
🅿️Closed Parking1
📅Completion2018-12-30
🏗️Proposed Floors5
Sanctioned5
🅿️Closed Parking1
📅Completion2018-12-30
🏗️Proposed Floors5
Sanctioned5
🅿️Closed Parking1
📅Completion2018-12-30
🏗️Proposed Floors5
Sanctioned5
🅿️Closed Parking1
📅Completion2018-12-30
🏗️Proposed Floors5
Sanctioned5
🅿️Closed Parking1
📅Completion2018-12-30
🏗️Proposed Floors5
Sanctioned5
🅿️Closed Parking1
📅Completion2018-12-30
🏗️Proposed Floors5
Sanctioned5
🅿️Closed Parking1
📅Completion2018-12-30
🏗️Proposed Floors5
Sanctioned5
🅿️Closed Parking1
📅Completion2018-12-30
🏗️Proposed Floors5
Sanctioned5
🅿️Closed Parking1
📅Completion2018-12-30
🏗️Proposed Floors5
Sanctioned5
🅿️Closed Parking1
📅Completion2018-12-30
🏗️Proposed Floors5
Sanctioned5
🅿️Closed Parking1
📅Completion2018-12-30

Apartment Configurations

A1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK47.82880
100%
3 BHK71.88880
100%

A2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK47.82880
100%
3 BHK71.88880
100%

B1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK48.0616160
100%

B2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK48.0616160
100%

B3

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK48.0616160
100%

E1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK49.2316160
100%

E2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK49.2316160
100%

F1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK29.51880
100%
2 BHK49.14880
100%

F2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK29.51880
100%
2 BHK49.14880
100%

F3

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK29.51880
100%
2 BHK49.14880
100%

F4

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK29.51880
100%
2 BHK49.14880
100%

F5

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK28.97880
100%
2 BHK42.75440
100%

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 Bhk28.969999313354492000
0%
1 Bhk29.510000228881836000
0%
2 Bhk42.75000
0%
2 Bhk47.81999969482422000
0%
2 Bhk48.060001373291016000
0%
2 Bhk49.13999938964844000
0%
2 Bhk49.22999954223633000
0%
3 Bhk71.87999725341797000
0%

Construction Progress

A1

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

A2

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

B1

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

B2

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

B3

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

E1

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

E2

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

F1

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

F2

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

F3

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

F4

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

F5

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

RERA Registered Amenities

Aggregate area of recreational Open Space20%
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station100%
Energy management100%
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting20%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)95%
Solid Waste Management And Disposal100%
Storm Water Drains100%
Street Lighting50%
Treatment And Disposal Of Sewage And Sullage Water95%
Water Conservation, Rain water Harvesting100%
Water Supply100%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.