RERA: A51800043517

SABARI ASHVILLE

by SABARI JANI ASSOCIATES Others
Certificate Signed P51800003066
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51800003066
Registration No.
REA51800007997
Registration Date
2017-08-04
Developer
SABARI JANI ASSOCIATES Others
Architect
Chandrakumar S Ruparel
Project Bank
KOTAK MAHINDRA BANK LIMITED
Proposed Possession
2017-12-31
Revised Possession
2017-12-31
Extended Possession
2018-12-31
Units Sold
0
Buildings
1
Project Area
2392.56 sq.m
Total FSI
5831.14
Approved FSI
5735.14
MahaRERA QR
SABARI ASHVILLE
MahaRERA — P51800003066
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors24
Sanctioned24
⬇️Basements2
🅿️Closed Parking1
📅Completion2018-12-31

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
2 Bhk 80.30000305175781 0 0 0
0%
3 Bhk 123.0 0 0 0
0%
4 Bhk 156.0 0 0 0
0%
5 Bhk 221.0 0 0 0
0%
5 Bhk 225.0 0 0 0
0%

Sabari Ashville

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 80.3 1 0 1
0%
3 BHK 123.0 20 15 5
75%
4 BHK 156.0 15 11 4
73%
5 BHK 221.0 1 0 1
0%
5 BHK 225.0 1 0 1
0%

Construction Progress

SABARI ASHVILLE

Basement (if any)100%

Sabari Ashville

Excavation100%

SABARI ASHVILLE

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Sabari Ashville

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

SABARI ASHVILLE

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Sabari Ashville

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%

SABARI ASHVILLE

Plinth100%
Podiums (if any) 100%

Sabari Ashville

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises99%

SABARI ASHVILLE

Sanitary Fittings within the flats / premises99%
Slabs of Super Structure100%

Sabari Ashville

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

SABARI ASHVILLE

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Sabari Ashville

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space 100%
Community Buildings 100%
Electrical Meter Room, Sub-Station, Receiving Station 99%
Energy management
Fire Protection And Fire Safety Requirements 100%
Landscaping & Tree Planting 100%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 100%
Solid Waste Management And Disposal
Storm Water Drains 100%
Street Lighting 100%
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting 100%
Water Supply 99%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.