Project Information

RERA Certificate No.
P51800004225
Registration No.
REA51800011801
Developer
Orbit Ventures &Amp; Co.
Project Bank
KOTAK MAHINDRA BANK
Proposed Possession
2022-12-31
Revised Possession
2024-12-30
Extended Possession
1900-01-01
Buildings
5
Project Area
7633.10 sq.m
Total FSI
22345.00
Approved FSI
15000.00
MahaRERA QR
The Chakravarti Ashok Chsl
MahaRERA — P51800004225
Scan to verify on MahaRERA portal

Wing-wise Details

⬇️Basements1
🅿️Closed Parking1
📅Completion2023-12-31
⬇️Basements1
🅿️Closed Parking1
📅Completion2023-12-31
⬇️Basements1
🅿️Closed Parking1
📅Completion2023-12-31
⬇️Basements1
🅿️Closed Parking1
📅Completion2023-12-31
⬇️Basements1
🅿️Closed Parking1
📅Completion2023-12-31

Apartment Configurations

Chakravarti Ashok Chsl Building No 2 A Wing

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 82.72 11 1 10
9%
2 BHK 85.0 11 2 9
18%
2 BHK 100.96 12 1 11
8%
3 BHK 86.96 13 0 13
0%
SHOP 49.68 1 0 1
0%
SHOP 80.3 1 0 1
0%
SHOP 91.88 1 0 1
0%

Chakravarti Ashok Chsl Building No 2 B Wing

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 79.3 11 2 9
18%
2 BHK 82.72 11 1 10
9%
2 BHK 85.95 13 0 13
0%
3 BHK 100.26 13 0 13
0%

The Chakravarti Ashok Chsl Building No 2 C Wing

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 66.13 9 4 5
44%
2 BHK 74.31 10 3 7
30%
2 BHK 81.52 12 0 12
0%
3 BHK 105.3 13 0 13
0%

The Chakravarti Ashok Chsl Building No 5

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 46.44 38 1 37
3%
1 BHK 46.61 13 0 13
0%

The Chakravarti Ashok Chsl Builing No 2 D Wing

Type Carpet (sq.ft) Total Booked Available Status
3 BHK 88.46 6 0 6
0%
3 BHK 97.34 2 0 2
0%

Construction Progress

Chakravarti Ashok Chsl Building No 2 A Wing

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth75%
X number of Podiums0%
X number of Slabs of Super Structure0%

Chakravarti Ashok Chsl Building No 2 B Wing

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing20%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure0%

The Chakravarti Ashok Chsl Building No 2 C Wing

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure25%

The Chakravarti Ashok Chsl Building No 5

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing41%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure10%

The Chakravarti Ashok Chsl Builing No 2 D Wing

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises7%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure50%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains 50%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.