Crescent Bay - T2

by L&T Parel Project Llp (Jv With Ordpl) Others
Certificate SignedP51900010178

Project Information

RERA Certificate No.
P51900010178
Registration No.
REA51900015690
Registration Date
2018-02-07
Developer
L&T Parel Project Llp (Jv With Ordpl) Others
Architect
Anand V. Dhokay
Project Bank
KOTAK MAHINDRA BANK LIMITED
Proposed Possession
2019-03-31
Revised Possession
2019-03-31
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
929.91 sq.m
Total FSI
20793.15
Approved FSI
20103.85
MahaRERA QR
Crescent Bay - T2
MahaRERA — P51900010178
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors57
Sanctioned57
🅿️Closed Parking390
📅Completion2019-03-31

Apartment Configurations

Crescent Bay - T2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK Premier A63.3976751
99%
2 BHK Premier B72.48847311
87%
2 BHK Premier C71.71880
100%
3 BHK Elegante A77.4934340
100%
3 BHK Elegante B85.0838335
87%

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2Bhk Premier A63.38999938964844000
0%
2Bhk Premier B72.4800033569336000
0%
2Bhk Premier C71.70999908447266000
0%
3Bhk Elegante A77.48999786376953000
0%
3Bhk Elegante B85.08000183105469000
0%

Construction Progress

Crescent Bay - T2

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.86%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate86%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station79%
Energy management65%
Fire Protection And Fire Safety Requirements98%
Jogging Track with Associated amenities74%
Landscaping & Tree Planting80%
NA
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)100%
Solid Waste Management And Disposal
Storm Water Drains80%
Street Lighting54%
Treatment And Disposal Of Sewage And Sullage Water100%
Water Conservation, Rain water Harvesting75%
Water Supply99%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.