📞 +91 98200 30685✉️
RERA: A51800043517

Crescent Nexus- (Ascent)

by Ascent Infraspace Private Limited
Certificate SignedP51800030043

Project Information

RERA Certificate No.
P51800030043
Registration No.
REA51800089589
Registration Date
2021-10-05
Developer
Ascent Infraspace Private Limited
Architect
Vishwas Satodia
Project Bank
INDUSIND BANK
Proposed Possession
2026-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
3
Project Area
5680.90 sq.m
Total FSI
11876.73
Approved FSI
8989.38
MahaRERA QR
Crescent Nexus- (Ascent)
MahaRERA — P51800030043
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors17
Sanctioned17
⬇️Basements1
🅿️Closed Parking71
📅Completion2025-12-31
🏗️Proposed Floors17
Sanctioned17
⬇️Basements1
🅿️Closed Parking71
📅Completion2026-12-31
🏗️Proposed Floors17
Sanctioned17
⬇️Basements1
🅿️Closed Parking71
📅Completion2025-12-31

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1Bhk41.060001373291016000
0%
1Bhk41.43000030517578000
0%
1Bhk41.619998931884766000
0%
1Bhk41.709999084472656000
0%
1Bhk41.72999954223633000
0%
1Rk29.079999923706055000
0%
2Bhk60.11000061035156000
0%
2Bhk60.38999938964844000
0%
2Bhk61.689998626708984000
0%
2Bhk62.79999923706055000
0%
Office Space150.02999877929688000
0%
Shop12.630000114440918000
0%
Shop13.5600004196167000
0%
Shop13.75000
0%
Shop14.859999656677246000
0%
Shop16.06999969482422000
0%
Shop18.299999237060547000
0%
Shop19.31999969482422000
0%
Shop21.270000457763672000
0%
Shop24.25000
0%

Bldg No 3- Crescent Downtown B Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK41.43770
100%
1 BHK41.7114140
100%
2 BHK60.39660
100%
Office space150.03101
0%
Shop12.63220
100%
Shop16.07110
100%
Shop18.3110
100%
Shop19.32110
100%
Shop24.25110
100%

Bldg No 3- Crescent Downtown D Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK41.43660
100%
1 BHK41.73880
100%
2 BHK60.11734
43%
2 BHK62.8761
86%

Bldg No 3-Crescent Downtown- A Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK41.06770
100%
1 BHK41.62660
100%
1RK29.0814122
86%
2 BHK61.69743
57%
Shop13.56110
100%
Shop13.75110
100%
Shop14.86110
100%
Shop21.27110
100%

Construction Progress

Bldg No 3- Crescent Downtown B wing

Basement (if any)100%

Bldg No 3- Crescent Downtown B Wing

Excavation100%

Bldg No 3- Crescent Downtown B wing

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Bldg No 3- Crescent Downtown B Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

Bldg No 3- Crescent Downtown B wing

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30%

Bldg No 3- Crescent Downtown B Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises30%
Overall Percentage of Completion of the work done For the entire Building /Wing43%

Bldg No 3- Crescent Downtown B wing

Plinth100%
Podiums (if any) 50%

Bldg No 3- Crescent Downtown B Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

Bldg No 3- Crescent Downtown B wing

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure50%

Bldg No 3- Crescent Downtown B Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.50%

Bldg No 3- Crescent Downtown B wing

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%

Bldg No 3- Crescent Downtown B Wing

Stilt Floor50%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums50%
X number of Slabs of Super Structure50%

Bldg No 3- Crescent Downtown D Wing

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing39%
Plinth100%
Podiums (if any) 50%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure60%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.30%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
Stilt Floor50%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums50%
X number of Slabs of Super Structure60%

Bldg No 3-Crescent Downtown- A Wing

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises90%
Overall Percentage of Completion of the work done For the entire Building /Wing74%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing50%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.