Daivi Eterneety

by Yash Development Partnership
Certificate SignedP51800029609

Project Information

RERA Certificate No.
P51800029609
Registration No.
REA51800088621
Registration Date
2022-02-02
Developer
Yash Development Partnership
Project Bank
AU SMALL FINANCE BANK LIMITED
Proposed Possession
2026-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
321
Units Sold
239 (74%)
Buildings
1
Project Area
3055.00 sq.m
Total FSI
32000.00
MahaRERA QR
Daivi Eterneety
MahaRERA — P51800029609
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors38
Sanctioned38
🏠Habitable20
⬇️Basements2
🅿️Closed Parking1
📅Completion2026-12-31

Apartment Configurations

Shreeji Daivi

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK A WING71.8126179
65%
2 BHK A WING77.1126179
65%
2 BHK B WING69.21261115
42%
2 BHK B WING70.79261511
58%
2 BHK B WING81.3831247
77%
3 BHK A WING89.65101
0%
3 BHK A WING99.9614140
100%
3 BHK A WING102.1915141
93%
3 BHK A WING102.9417107
59%
3 BHK A WING107.1216106
62%
3 BHK B WING89.65101
0%
3 BHK B WING99.8714131
93%
3 BHK B WING100.1514140
100%
3 BHK B WING102.8431238
74%
3 BHK B WING103.416106
62%
3 BHK B WING105.1716106
62%
4 BHK A WING162.6731229
71%

Construction Progress

DAIVI ETERNEETY

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises43%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure47%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
Stilt Floor 100%

Shreeji Daivi

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.23%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure33%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.