Dinaco Darshan CHS LTD
by Dinaco Darshan CHSL
Society
Project Information
RERA Certificate No.
P51800032422
Registration No.
REA51800100678
Registration Date
2023-07-28
Developer
Dinaco Darshan CHSL Society
Architect
Umesh Gawde
Project Bank
HDFC BANK
Proposed Possession
2024-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
960.53 sq.m
Total FSI
2588.18
Approved FSI
940.67
Dinaco Darshan CHS LTD
MahaRERA — P51800032422
MahaRERA — P51800032422
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors16
✅Sanctioned16
🚗Open
Parking13
🅿️Closed Parking20
📅Completion2024-12-31
Apartment Configurations
None
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1Bhk | 31.09000015258789 | 0 | 0 | 0 | 0% |
| 1Bhk | 34.75 | 0 | 0 | 0 | 0% |
| 1Bhk | 34.95000076293945 | 0 | 0 | 0 | 0% |
| 1Bhk | 38.66999816894531 | 0 | 0 | 0 | 0% |
| 1Bhk | 39.4900016784668 | 0 | 0 | 0 | 0% |
| 1Bhk | 40.66999816894531 | 0 | 0 | 0 | 0% |
| 1Bhk | 44.20000076293945 | 0 | 0 | 0 | 0% |
| 2Bhk | 50.33000183105469 | 0 | 0 | 0 | 0% |
Dinaco Darshan Chs Ltd
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 31.12 | 1 | 1 | 0 | 100% |
| 1 BHK | 34.74 | 6 | 6 | 0 | 100% |
| 1 BHK | 34.93 | 1 | 1 | 0 | 100% |
| 1 BHK | 38.65 | 6 | 6 | 0 | 100% |
| 1 BHK | 39.49 | 2 | 2 | 0 | 100% |
| 1 BHK | 40.69 | 1 | 0 | 1 | 0% |
| 2 BHK | 44.22 | 5 | 4 | 1 | 80% |
| 2 BHK | 50.35 | 2 | 2 | 0 | 100% |
Construction Progress
Dinaco Darshan CHS Ltd
Dinaco Darshan Chs Ltd
Dinaco Darshan CHS Ltd
Dinaco Darshan Chs Ltd
Dinaco Darshan CHS Ltd
Dinaco Darshan Chs Ltd
Dinaco Darshan CHS Ltd
Dinaco Darshan Chs Ltd
Dinaco Darshan CHS Ltd
Dinaco Darshan Chs Ltd
Dinaco Darshan CHS Ltd
Dinaco Darshan Chs Ltd
RERA Registered Amenities
⬜
Aggregate area of recreational Open Space
⬜
Community Buildings
✅
Electrical Meter Room, Sub-Station, Receiving Station
50%
⬜
Energy management
✅
Fire Protection And Fire Safety
Requirements
✅
Landscaping & Tree Planting
✅
Open Parking
✅
Sewerage (Chamber, Lines, Septic Tank , STP)
90%
✅
Solid Waste Management And Disposal
85%
✅
Storm Water Drains
⬜
Street Lighting
⬜
Treatment And Disposal Of Sewage And Sullage Water
✅
Water Conservation, Rain water Harvesting
90%
✅
Water Supply
60%