Elanza
by A R Constructions
Partnership
Project Information
RERA Certificate No.
P51900000604
Registration No.
REA51900003707
Registration Date
2017-07-18
Developer
A R Constructions Partnership
Architect
Arch Vision
Project Bank
RBL Bank Limited
Proposed Possession
2018-03-31
Revised Possession
2018-03-31
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
1791.82 sq.m
Total FSI
5714.04
Approved FSI
5714.04
Elanza
MahaRERA — P51900000604
MahaRERA — P51900000604
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors24
✅Sanctioned24
🅿️Closed Parking63
📅Completion1900-01-01
Apartment Configurations
None
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 2Bhk | 74.56999969482422 | 0 | 0 | 0 | 0% |
| 2Bhk | 74.77999877929688 | 0 | 0 | 0 | 0% |
| 2Bhk | 75.29000091552734 | 0 | 0 | 0 | 0% |
| 2Bhk | 75.5 | 0 | 0 | 0 | 0% |
| Multipurposeroom | 25.3799991607666 | 0 | 0 | 0 | 0% |
| Multipurposeroom | 25.8799991607666 | 0 | 0 | 0 | 0% |
| Multipurposeroom | 26.020000457763672 | 0 | 0 | 0 | 0% |
| Multipurposeroom | 26.3700008392334 | 0 | 0 | 0 | 0% |
| Multipurposeroom | 31.06999969482422 | 0 | 0 | 0 | 0% |
| Multipurposeroom | 38.880001068115234 | 0 | 0 | 0 | 0% |
| Multipurposeroom | 39.029998779296875 | 0 | 0 | 0 | 0% |
Elanza
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 2 BHK | 74.57 | 18 | 2 | 16 | 11% |
| 2 BHK | 74.78 | 18 | 5 | 13 | 28% |
| 2 BHK | 75.29 | 2 | 0 | 2 | 0% |
| 2 BHK | 75.5 | 2 | 0 | 2 | 0% |
| MultiPurposeRoom | 25.38 | 1 | 0 | 1 | 0% |
| MultiPurposeRoom | 25.88 | 1 | 0 | 1 | 0% |
| MultiPurposeRoom | 26.02 | 2 | 0 | 2 | 0% |
| MultiPurposeRoom | 26.37 | 1 | 0 | 1 | 0% |
| MultiPurposeRoom | 31.07 | 2 | 0 | 2 | 0% |
| MultiPurposeRoom | 38.88 | 1 | 0 | 1 | 0% |
| MultiPurposeRoom | 39.03 | 1 | 0 | 1 | 0% |
Construction Progress
Elanza
RERA Registered Amenities
✅
Aggregate area of recreational Open Space
⬜
Community Buildings
✅
Electrical Meter Room, Sub-Station, Receiving Station
⬜
Energy management
✅
Fire Protection And Fire Safety
Requirements
20%
✅
Landscaping & Tree Planting
⬜
Open Parking
✅
Sewerage (Chamber, Lines, Septic Tank , STP)
75%
⬜
Solid Waste Management And Disposal
✅
Storm Water Drains
⬜
Street Lighting
⬜
Treatment And Disposal Of Sewage And Sullage Water
✅
Water Conservation, Rain water Harvesting
✅
Water Supply